Q. 931: Which of the following reduces the probability of the potential consequences of project risk events?
A. Preventive action
B. Risk management
C. Corrective action
D. Defect repair
Section: Initiation
<<<<<< =================== >>>>>>
Q. 932: Ensuring that projects and programs are reviewed to prioritize resource allocation is a focus of which of the following?
A. Project management
B. Program management
C. Portfolio management
D. Relationship management
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 933: In a weak matrix, the project managers role is:
A. part-time
B. full-time
C. occasional
D. unlimited
Section: Closing
<<<<<< =================== >>>>>>
Q. 934: Testing falls into which of the following categories of cost of quality?
A. Internal failure costs
B. Prevention costs
C. Appraisal costs
D. External failure costs
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 935: An input to the Identify Stakeholders process is:
A. The project management plan.
B. The stakeholder register.
C. Procurement documents.
D. Stakeholder analysis.
Section: Executing
<<<<<< =================== >>>>>>
Q. 936: Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?
A. Project sponsor and project manager
B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager
Section: Initiation
<<<<<< =================== >>>>>>
Q. 937: A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
A. mitigate
B. accept
C. transfer
D. avoid
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 938: In Project Cost Management, which input is exclusive to the Determine Budget process?
A. Scope baseline
B. Organizational process assets
C. Project schedule
D. Resource calendars
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 939: An input to Close Project or Phase is:
A. Accepted deliverables,
B. Final products or services.
C. Document updates.
D. Work performance information.
Section: Closing
<<<<<< =================== >>>>>>
Q. 940: Which of the following are examples of interactive communication?
A. Intranet sites
B. Voice mails
C. Video conferences
D. Press releases
Section: Executing