PMI PMP-Project Management Professional Practice Exam Q. 921 to 930
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 921: Which of the following is not relevant for analogous estimation?
A. Historical records
B. Expert judgment
C. Project team member knowledge
D. Bottom-up estimating
Section: Planning
Justification in favor of the correct answer:
Bottom-up estimating technique estimates the cost of individual activities then “roll ups” to higher levels, which gives a more accurate estimate.
<<<<<< =================== >>>>>>
Q. 922: The cost performance baseline is typically displayed in the form of:
A. An S-curve.
B. A normal curve.
C. A U-curve.
D. A positive slope line.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 923: Which of the following is the primary output of the Identify Risks process?
A. Risk management plan
B. Risk register
C. Change requests
D. Risk response plan
Section: Initiation
<<<<<< =================== >>>>>>
Q. 924: The project charter is an input to which process?
A. Develop Project Charter
B. Develop Project Management Plan
C. Monitor and Control Project Work
D. Perform Integrated Change Control
Section: Initiation
<<<<<< =================== >>>>>>
Q. 925: When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
A. training, testing, and warranty work.
B. equipment, rework, and scrap.
C. training, document processes, and inspections.
D. inspections, rework, and warranty work.
Section: Closing
<<<<<< =================== >>>>>>
Q. 926: Ideally, a project manager should be selected and assigned at which point in the project life cycle?
A. During the initiating processes
B. During the project planning process
C. At the end of the concept phase of the project life cycle
D. Prior to the beginning of the development phase of the project life cycle
Section: Mix Questions
Justification in favor of the correct answer:
When the project manager is selected and assigned to the project during initiation, several of the usual start-up tasks for a project are simplified. In addition, becoming involved with project activities from the beginning helps the project manager to understand where the project fits within the organization in terms of its priority relative to other projects and the ongoing work of the organization.
<<<<<< =================== >>>>>>
Q. 927: Which quality control technique illustrates the 80/20 principle?
A. Ishikawa diagram
B. Control chart
C. Run chart
D. Pareto chart
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 928: High-level project risks are included in which document?
A. Business case
B. Risk breakdown structure
C. Project charter
D. Risk register
Section: Initiation
<<<<<< =================== >>>>>>
Q. 929: Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
A. Cost-reimbursable contracts
B. Time and Material contracts (T&M)
C. Fixed-price contracts
D. Cost Plus Fixed Fee Contracts (CPFF)
Section: Closing
<<<<<< =================== >>>>>>
Q. 930: Which enterprise environmental factors are considered during Estimate Costs?
A. Market conditions and published commercial information
B. Company structure and market conditions
C. Commercial information and company structure
D. Existing human resources and market conditions
Section: Monitoring and Controlling
Access the full Database of All Questions
An expert on R&D, Online Training and Publishing. He is M.Tech. (Honours) and is a part of the STG team since inception.