PMI PMP-Project Management Professional Practice Exam Q. 911 to 920
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 911: Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
A. Initiating
B. Planning
C. Executing
D. Closing
Section: Executing
<<<<<< =================== >>>>>>
Q. 912: What characteristic do project and operational work share in common?
A. Performed by systems
B. Constrained by limited resources
C. Repetitiveness
D. Uniqueness
Section: Initiation
<<<<<< =================== >>>>>>
Q. 913: Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
A. Analogous
B. Parametric
C. Bottom-up
D. Top-down
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 914: If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A. One
B. Five
C. Six
D. Seven
Section: Closing
<<<<<< =================== >>>>>>
Q. 915: Which action is included in the Control Costs process?
A. Identify how the project costs will be planned, structured, and controlled
B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
C. Develop an approximation of the monetary resources needed to complete project activities
D. Monitor cost performance to isolate and understand variances from the approved cost baseline
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 916: Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A. WBS directory
B. Activity list
C. WBS
D. Project scheduleSection: Initiation
Section: Initiation
<<<<<< =================== >>>>>>
Q. 917: Stakeholder communication requirements should be included as a component of:
A. enterprise environmental factors
B. organizational process assets
C. the project management plan
D. the stakeholder register
Section: Planning
<<<<<< =================== >>>>>>
Q. 918: Market conditions and published commercial information are examples of which input to the Estimate Costs process?
A. Scope baseline
B. Organizational process assets
C. Enterprise environmental factors
D. Risk register
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 919: Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 920: A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
A. To the project management plan.
B. To the risk register.
C. In the scope verification processes.
D. And their impact to the project in terms of time, cost, and risk.
Section: Executing