Q. 901: Which technique helps to determine the risks that have the most potential impact on a project?
A. Cost risk simulation analysis
B. Expected monetary value analysis
C. Modeling and simulation
D. Sensitivity analysis
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 902: The product scope description is used to:
A. Gain stakeholders’ support for the project.
B. Progressively elaborate the characteristics of the product, service, or result.
C. Describe the project in great detail.
D. Define the process and criteria for accepting a completed product, service, or result.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 903: Working on your project management training curricula project, you decided it would be beneficial to you to become an active member of the Project Management Institute as part of the objectives of your project is to ensure it is aligned with PMI’s best practices. To complement PMI’s Work Breakdown Structure Practice Standard, you learned PMI was requesting volunteers to participate in developing a similar standard on the Scope Statement. You volunteered, and now the Standard is issued. This is an example of:
A. Improving your own competency as a project manager
B. Corrective action
C. Preventive action
D. A requirement for you to immediately update your project management plan
Section: Mix Questions
Justification in favor of the correct answer:
When you volunteered, you signed a confidentiality statement so you could not disclose what was under way on this activity. Now the Standard has been issued, and to stay in alignment with PMICRYs best practices, you need to issue change request based on corrective action to realign the performance of the work of your project with your project management plan.
<<<<<< =================== >>>>>>
Q. 904: Which process should be conducted from the project inception through completion?
A. Monitor and Control Project Work
B. Perform Quality Control
C. Perform Integrated Change Control
D. Monitor and Control Risks
Section: Executing
<<<<<< =================== >>>>>>
Q. 905: At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
A. Result
B. Product
C. Service
D. Improvement
Section: Closing
<<<<<< =================== >>>>>>
Q. 906: Work performance information and cost forecasts are outputs of which Project Cost Management process?
A. Estimate Costs
B. Plan Cost Management
C. Determine Budget
D. Control Costs
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 907: Which of the following is an input to Control Scope?
A. Project schedule
B. Organizational process assets updates
C. Project document updates
D. Work performance information
Section: Planning
<<<<<< =================== >>>>>>
Q. 908: On 26th of Sept, Robin, an executive of an Airlines called me and said, “I can finally give you Singapore-New Delhi air contract at $1850.” What kind of contract does this case resembles?
A. Time and Material
B. Fixed Price
C. Cost Reimbursable
D. Cost Plus Incentive
Section: Planning
Justification in favor of the correct answer:
In this type of contract, one price is agreed upon for all the work from Singapore to New Delhi at $1850.
<<<<<< =================== >>>>>>
Q. 909: What is a hierarchically organized depiction of the identified project risks arranged by risk category?
A. Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan
D. Risk category
Section: Initiation
<<<<<< =================== >>>>>>
Q. 910: You want to minimize the impact of changes on your project, yet you want to ensure that change is managed when and if it occurs. This can be done through each of the following ways EXCEPT:
A. Rejecting requested changes
B. Approving changes and incorporating them into a revised baseline
C. Documenting the complete impact of requested changes
D. Ensuring that project scope changes are reflected in changes to product scope
Section: Mix Questions
Justification in favor of the correct answer:
Integrated change control requires maintaining the integrity of baselines by releasing only approved changes into project products, services, or results. It also ensures that changes to product scope are reflected in the project scope definition. This is done by coordinating changes across the entire project.