PMI PMP-Project Management Professional Practice Exam Q. 791 to 800
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 791: The process for performing variance analysis may vary, depending on:
A. scenario building. technology forecasting, and forecast by analogy.
B. working relationships among various stakeholders and team members.
C. application area, the standard used, and the industry,
D. work to be completed next.
Section: Closing
<<<<<< =================== >>>>>>
Q. 792: In which process is a project manager identified and given the authority to apply resources to project activities?
A. Acquire Project Team
B. Develop Project Management Plan
C. Manage Project Execution
D. Develop Project Charter
Section: Initiation
<<<<<< =================== >>>>>>
Q. 793: Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
A. Stakeholder register
B. Scope management plan
C. Stakeholder management plan
D. Project charter
Section: Initiation
<<<<<< =================== >>>>>>
Q. 794: Information collected on the status of project activities being performed to accomplish the project work is known as what?
A. Project management information system
B. Work performance information
C. Work breakdown structure
D. Variance analysis
Section: Closing
<<<<<< =================== >>>>>>
Q. 795: Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
A. updates.
B. defect repairs.
C. preventive actions.
D. corrective actions.
Section: Planning
<<<<<< =================== >>>>>>
Q. 796: Which of the following is a complete set of indexed contract documentation, including the closed contract?
A. Procurement package
B. Negotiated settlements
C. Procurement file
D. Procurement management plan
Section: Closing
<<<<<< =================== >>>>>>
Q. 797: Which of the following is an output of the Distribute Information process?
A. Project calendar
B. Communications management plan
C. Organizational process assets updates
D. Project document updates
Section: Initiation
<<<<<< =================== >>>>>>
Q. 798: Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?
A. Gantt chart
B. Project schedule network diagram
C. Project milestone list
D. Activity list
Section: Executing
<<<<<< =================== >>>>>>
Q. 799: The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
A. adaptive
B. reflexive
C. predictive
D. iterative
Section: Executing
Q. 800: Which is the document that presents a hierarchical project organization?
A. WBS
B. CPI
C. OBS
D. BOM
Section: Initiation