PMI PMP-Project Management Professional Practice Exam Q. 781 to 790
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 781: An output of the Create WBS process is:
A. Scope baseline.
B. Project scope statement.
C. Organizational process assets.
D. Requirements traceability matrix.
Section: Planning
<<<<<< =================== >>>>>>
Q. 782: Which process determines the risks that might affect the project?
A. Perform Qualitative Risk Analysis
B. Identify Risks
C. Plan Risk Management
D. Perform Quantitative Risk Analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 783: The formal and informal interaction with others in an organization, industry, or professional environment is known as:
A. negotiation
B. organizational theory
C. meeting
D. networking
Section: Initiation
<<<<<< =================== >>>>>>
Q. 784: The cost of nonconformance in a project includes:
A. testing
B. rework
C. inspections
D. training
Section: Executing
<<<<<< =================== >>>>>>
Q. 785: The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50.000, Plan cost = $45.000. Earned value = $40.000. What is the cost performance index?
A. 0.8
B. 0.89
C. 1.13
D. 1.25
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 786: The number of potential communication channels for a project with 5 stakeholders is:
A. 10.
B. 12.
C. 20.
D. 24.
Section: Executing
<<<<<< =================== >>>>>>
Q. 787: Which is a communication method used in the Report Performance process?
A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 788: What does a CPI value greater than 1.0 indicate?
A. Cost right at the estimated value
B. Cost under the estimated value
C. Cost right at the actual value
D. Cost over the estimated value
Section: Executing
<<<<<< =================== >>>>>>
Q. 789: Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
A. Facilitation techniques
B. Expert judgment
C. Analytical techniques
D. Variance analysis
Section: Planning
<<<<<< =================== >>>>>>
Q. 790: The following is the network diagram for a project:
What is the critical path for the project?
A. A-B-C-F-G-I
B. A-B-C-F-H-I
C. A-D-E-F-G-I
D. A-D-E-F-H-I
Section: Planning