Q. 661: During what process is the quality policy determined?
A. Initiating
B. Executing
C. Planning
D. Controlling
Section: Planning
<<<<<< =================== >>>>>>
Q. 662: Which activity involves ensuring that the composition of a projects configuration items is correct?
A. Configuration Identification
B. Configuration Status Accounting
C. Configuration Verification and Audit
D. Configuration Quality Assurance
Section: Executing
<<<<<< =================== >>>>>>
Q. 663: You can purchase software licenses for your project at $1,000 per user. You have 10 users, so you predict your costs will be $10,000. This is an example of which cost estimating approach?
A. Parametric estimating
B. Analogous estimating
C. Bottom-up estimating
D. Top-down estimating
Section: Planning
Justification in favor of the correct answer:
The method described in the questions is known as parametric estimating, which is where you multiply a known statistical cost per unit by the number of units. In this case 10 times $1,000 is $10,000.
<<<<<< =================== >>>>>>
Q. 664: Which of the following is a tool and technique used in the Develop Schedule process?
A. Three-point estimates
B. Resource leveling
C. Precedence diagramming method
D. Bottom-up estimating
Section: Initiation
<<<<<< =================== >>>>>>
Q. 665: The following is a network diagram for a project:
The free float for Activity E is how many days?
A. 2
B. 3
C. 5
D. 8
Section: Planning
<<<<<< =================== >>>>>>
Q. 666: An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
A. Forecasting.
B. Brainstorming.
C. Historical databases.
D. Cost of quality.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 667: How is a context diagram used?
A. To depict product scope
B. To trace requirements as part of the traceability matrix
C. To develop the scope management plan
D. To develop the requirements management plan
Section: Mix Questions
Justification in favor of the correct answer:
It is a tool and technique in collect requirements and is an example of a scope model. The context diagram visually depicts the product scope as it shows a business system (process, equipment, or computer, etc.) and how people and other systems (actors) interact with it. The diagram shows inputs to the business system, the actor(s) providing the input, outputs from the business system, and actor(s) receiving the output.
<<<<<< =================== >>>>>>
Q. 668: The process to ensure that appropriate quality standards and operational definitions are used is:
A. Plan Quality.
B. Perform Quality Assurance.
C. Perform Quality Control.
D. Total Quality Management.
Section:Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 669: In which process might you use risk reassessment as a tool and technique?
A. Qualitative risk analysis
B. Risk monitoring and control
C. Monitor and control project work
D. Risk response planning
Section: Executing
<<<<<< =================== >>>>>>
Q. 670: Assigned risk ratings are based upon:
A. Root cause analysis.
B. Risk probability and impact assessment.
C. Expert judgment.
D. Revised stakeholders’ tolerances.
Section: Initiation