PMI PMP-Project Management Professional Practice Exam Q. 651 to 660
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 651: Which process involves determining, documenting, and managing stakeholders’ needs and requirements to meet project objectives?
A. Collect Requirements
B. Plan Scope Management
C. Define Scope
D. Define Activities
Section: Initiation
<<<<<< =================== >>>>>>
Q. 652: The following is a network diagram for a project:
The total float for the project is how many days?
A. 5
B. 9
C.12
D.14
Section: Planning
<<<<<< =================== >>>>>>
Q. 653: In the following diagram, if a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
A. -1
B. 0
C. 2
D. Cannot be determined
Section: Mix Questions
Justification in favor of the correct answer:
The imposed finish date becomes the late finish for Activity I. The late dates for each activity need to be recalculated. The dates for Activity E become
ES = 10
EF = 13
LS = 9LF = 12
Total float = LS – ES or 9 – 10 = (-1) or
LS – EF or 12 – 13 = (-1)
<<<<<< =================== >>>>>>
Q. 654: Which type of team can be defined as a group of people with a shared goal who fulfill their roles although spending little or no time meeting face to face?
A. Co-location team
B. Virtual team
C. Departmental team
D. Consultant team
Section: Executing
<<<<<< =================== >>>>>>
Q. 655: Which of the following is an input to Develop Human Resource Plan?
A. Team performance assessment
B. Roles and responsibilities
C. Staffing management plan
D. Enterprise environmental factors
Section: Planning
<<<<<< =================== >>>>>>
Q. 656: Which Process Group’s purpose is to track, review, and regulate the progress and performance of the project: identify any areas in which changes to the plan are required, and initiate the corresponding changes?
A. Monitoring and Controlling
B. Initiating
C. Planning
D. Executing
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 657: Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
A. Interrelationship digraphs
B. Tree diagram
C. Affinity diagram
D. Network diagram
Section: Planning
<<<<<< =================== >>>>>>
Q. 658: Which type of organizational structure is displayed in the diagram provided?
A. Balanced matrix
B. Projectized
C. Strong matrix
D. Functional
Section: Planning
<<<<<< =================== >>>>>>
Q. 659: Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
A. Control Scope
B. Collect Requirements
C. Create WBS
D. Define Scope
Section: Initiation
<<<<<< =================== >>>>>>
Q. 660: Outputs of the Control Communications process include:
A. expert judgment and change requests.
B. work performance information and change requests.
C. organizational process asset updates and an issue log.
D. project management plan updates and an issue log.
Section: Planning