PMI PMP-Project Management Professional Practice Exam Q. 601 to 610
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 601: Which baselines make up the performance measurement baseline?
A. Scope baseline, cost baseline, and schedule baseline
B. Scope baseline, project management baseline, and quality baseline
C. Cost baseline, schedule baseline, and rick baseline
D. Cost baseline, project management baseline, and schedule baseline
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 602: Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
A. Analogous Estimating
B. Expert Judgment
C. Optimistic Estimates
D. Reserve Analysis
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 603: In the following diagram; what is the duration of the critical path in this network?
A. 10
B. 12
C. 14
D. 15
Section: Mix Questions
<<<<<< =================== >>>>>>
Q. 604: An input required in Define Scope is an organizational:
A. structure.
B. process asset.
C. matrix.
D. breakdown structure.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 605: Which of the following is an input into the Develop Project Team process?
A. Enterprise environmental factors
B. Organizational process assets
C. Project staff assignments
D. Performance reports
Section: Executing
<<<<<< =================== >>>>>>
Q. 606: The person assigned by the performing organization to be responsible for achieving the project objectives is the:
A. functional manager
B. program manager
C. project manager
D. portfolio manager
Section: Closing
<<<<<< =================== >>>>>>
Q. 607: When a control chart is used to monitor the performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?
A. Upper and lower control limits
B. Upper and lower specification limits
C. Process Mean
D. Data points
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 608: An input to the Collect Requirements process is the:
A. stakeholder register.
B. project management plan.
C. project scope statement.
D. requirements management plan.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 609: Work performance information includes all the following EXCEPT:
A. Started deliverables
B. Costs authorized and incurred
C. Progress of deliverables
D. Completed deliverables
Section: Mix Questions
Justification in favor of the correct answer:
Work performance information is an output of validate scope. It emphasizes deliverables whether or not they have started, their progress, and ones that have finished or have been accepted.
<<<<<< =================== >>>>>>
Q. 610: The integrative nature of project management requires which Process Group to interact with the other Process Groups?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Project Management
Section: Executing