PMI PMP-Project Management Professional Practice Exam Q. 271 to 280
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 271: Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
A. Performance organizations
B. Schedule baselines
C. Work performance measurements
D. Change requests
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 272: Which of the following techniques is used during Control Scope?
A. Cost-benefit analysis
B. Variance analysis
C. Reserve analysis
D. Stakeholder analysis
Section: Executing
<<<<<< =================== >>>>>>
Q. 273: You are managing a complex project for a new method of heating and air conditioning in vehicles. You will use both solar and wind technologies in this project to reduce energy costs. Therefore, you must ensure that the work of your project will result in delivering the project’s specified scope, which means that you should measure completion of the product scope against the:
A. Scope management plan
B. Project management plan
C. Product requirements
D. Requirements management plan
Section: Mix Questions
Justification in favor of the correct answer:
Completion of the project scope is measured against the project management plan, and completion of the product scope is measured against the requirements. In the project context. product scope consists of features and functions that characterize the product, service, or result. Project scope is the work that must be done to deliver the product, service, or result with specified features and functions.
<<<<<< =================== >>>>>>
Q. 274: The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
A. dictionary.
B. chart.
C. report.
D. register.
Section: Planning
<<<<<< =================== >>>>>>
Q. 275: You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are:
A. Start-to-finish
B. Finish-to-start
C. Start-to-start
D. Finish-to-finish
Section: Mix Questions
Justification in favor of the correct answer:
The completion of the work of the successor activity depends upon the completion of the work of the predecessor activity.
<<<<<< =================== >>>>>>
Q. 276: Which of the following is contained within the communications management plan?
A. An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors
Section: Planning
<<<<<< =================== >>>>>>
Q. 277: You are fairly new to managing a project but have been a team member for many years. You are pleased you were selected to manage your company’s 2018 model line of hybrid vehicles. You are now planning your project and have been preparing the subsidiary plans as well. You realize some project documents also are required to help manage your project. An example of one that you believe will be especially helpful is the:
A. Business case
B. Key performance indicators
C. Project management information system
D. Project statement of work
Section: Mix Questions
Justification in favor of the correct answer:
The project statement of work is a useful document as it describes the products, services, or results the project is to deliver. It references the business need, product scope description, and the strategic plan.
<<<<<< =================== >>>>>>
Q. 278: You work for a software development company that has followed the waterfall development model for more than 20 years. Lately, a number of customers have complained that your company is taking too long to complete its projects. You attended a class on agile development methods and believe that if the company used the agile approach, it could provide products to clients in a shorter time period. However, it would be a major culture change to switch from the waterfall methodology to the agile approach and to train staff members in this new approach. You mentioned this idea to the director of the PMO, and although she liked the idea, she would need approval from the company’s portfolio review board to move forward with it. She suggested that you document this idea in a:
A. Business need
B. Product scope description
C. Project charter
D. Business case
Section:Mix Questions
Justification in favor of the correct answer:
The business case is used to provide the necessary information to determine whether or not a project is worth its investment. It is used to justify the project and typically contains a cost-benefit analysis and a business need.
<<<<<< =================== >>>>>>
Q. 279: Administer Procurements is part of which Process Group?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Closing
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 280: Portfolio Management is the management of:
A. a project by dividing the project into more manageable sub-projects.
B. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing. and controlling.
C. all projects are undertaken by a company.
D. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.
Section: Planning