Quality Center Certification Skill Test: Q. 401 to 410
Objective Type / Multiple Choice Questions on QC � Quality Center 11.0 under the Series
(Quickly Review Your QC Skills before appearing for HP Certification Exam)
Set of 10 Questions
Correct Answers to Earlier Questions – Q. 391 to Q 400 are as under:
Q. 401: Which module enables you to define graphs and reports?
A. Test Plan
B. Test Resources
C. Dashboard
D. Requirements
<<<<<< =================== >>>>>>
Q. 402: What does the term severity refer to?
A. Importance level of the defect
B. Impact of the defect on the release goals
C. Impact of the defect on the test set
D. Impact of the defect on system operation
<<<<<< =================== >>>>>>
Q. 403: What should you use to gather and display the information in Quality Center? (Select three.)
A. External reports and graphs
B. Predefined reports and graphs
C. Document generator
D. User-defined reports and graphs
E. Custom reports and graphs
F.Custom document generator
<<<<<< =================== >>>>>>
Q. 404: You want to view the child requirements data related to the tests that the requirements cover. Which graph type should you use to accomplish this?
A. Progress graph
B. Trend graph
C. Requirements coverage graph
D. Summary graph
<<<<<< =================== >>>>>>
Q. 405: Which graph provides a visual overview of all the tests within a folder in the Test Plan Tree?
A. Visual analysis graph
B. Live analysis graph
C. Trend analysis graph
D. Summary graph
<<<<<< =================== >>>>>>
Q. 406: Your project manager wants to see a list of test instances and the results. Which type of report should you create to accomplish this?
A. Cross Test Set
B. Execution
C. Test Plan
D. Execution Status
<<<<<< =================== >>>>>>
Q. 407: You need to generate a report to monitor requirements and test coverage. Which report type should you use to accomplish this? (Select two.)
A. Standard
B. Predefined
C. Non-standard
D. Non-customized
E. Custom
<<<<<< =================== >>>>>>
Q. 408: What is a release?
A.A subset of the new features implemented in an application that has undergone a series of test cycles
B.A set of tests designed for a specific purpose such as new feature functionality, security, and performance
C.A group of test cycles that has been completed within a specific time period and in which all the high priority defects have been closed
D.A version of an application representing a group of changes that is available for distribution to customers at the same time
<<<<<< =================== >>>>>>
Q. 409: What is a cycle?
A.A subset of the new features implemented in an application that has undergone a series of test cycles
B.A set of tests designed for a specific purpose such as new feature functionality, security, and performance
C.A set of development and quality assurance efforts that is performed to achieve a common goal based on the release timeline
D.A version of an application representing a group of changes that is available for distribution to customers at the same time
<<<<<< =================== >>>>>>
Q. 410: Which requirement type needs to be defined as a custom type?
A. Business
B. Group
C. Functional
D. Testing
E. Security
Read the Correct Answer of the above Questions
Access the Full Database of All Questions
Correct Answers to Earlier Questions – Q. 391 to Q 400 are as under:
Question No. | Correct Answer |
Q. 391 | In Picture |
Q. 392 | A,C,D,G |
Q. 393 | A |
Q. 394 | A |
Q. 395 | In Picture |
Q. 396 | D |
Q. 397 | C |
Q. 398 | A,E |
Q. 399 | C |
Q. 400 | D |