Q. 131: The requirements _________ is a graphical representation of your requirements specification, displaying the hierarchical relationship between different requirements.
A. Graph
B. Plan
C. Path
D. Tree
<<<<<< =================== >>>>>>
Q. 132: For each requirement topic, a QA tester creates a list of __________ in the requirements tree.
A. Detailed requirements
B. Detailed specifications
C. Detailed plans
D. Detailed sub-requirements
<<<<<< =================== >>>>>>
Q. 133: Each requirement in the tree is described in detail and cannot include any relevant attachments.
A. True
B. False
<<<<<< =================== >>>>>>
Q. 134: After defining your requirements, you can add traceability between the requirements. When analyzing the impact of a change proposed in a specific requirement _________ shows the other requirements that the change might affect.
A. Equality
B. Link-ability
C. Traceability
D. Cross-links
<<<<<< =================== >>>>>>
Q. 135: QA managers assign the requirements to releases and cycles in the releases tree in the Releases module.
A. True
B. False
<<<<<< =================== >>>>>>
Q. 136: The assigned requirements are then used as a basis for the test plan in the Test Plan module. The tests you create during the test plan phase are then linked to these requirements to create _______
A. Linkages
B. Linked-requirements
C. Requirements plan
D. Coverage
<<<<<< =================== >>>>>>
Q. 137: QA managers review the requirements, they change a requirement from a Not Reviewed status to a _______ Status once it is approved.
A. Passed
B. Reviewed
C. Partially reviewed
D. Both B & C
<<<<<< =================== >>>>>>
Q. 138: You can also import requirements to your Quality Center project from ________
A. Microsoft Word
B. Excel
C. Other third-party requirement management tools
D. All of above
<<<<<< =================== >>>>>>
Q. 139: In the Requirements Tree view, Indicator columns indicates that the specified requirement has
A. Attachments, linked defects, alerts, and follow up flags
B. Attachments, linked defects, alerts
C. Attachments, linked defects and follow up flags
D. Linked defects, alerts, and follow up flags
<<<<<< =================== >>>>>>
Q. 140: To find a specific requirement by ReqID in the Requirements Tree view, choose __________ and enter the requirement ID.
A. Requirements > Find Requirement
B. Requirements > Go to Requirement
C. Requirements > Get Requirement
D. Requirements > Display Requirement
Read the Correct Answer of the above Questions
Access the Full Database of All Questions
Correct Answers to Earlier Questions – Q. 121 to Q 130 are as under:
Question No. | Correct Answer |
Q. 121 | C |
Q. 122 | E |
Q. 123 | A |
Q. 124 | B |
Q. 125 | A |
Q. 126 | B |
Q. 127 | A |
Q. 128 | C |
Q. 129 | B |
Q. 130 | B |