Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 881: What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
A. 0.03
B. 0.06
C. 0.10
D. 0.50
Section: Initiation
<<<<<< =================== >>>>>>
Q. 882: Which can be used to determine whether a process is stable or has predictable performance?
A. Matrix diagram
B. Histogram
C. Control chart
D. Flowchart
Section: Planning
<<<<<< =================== >>>>>>
Q. 883: Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
A. Procurement documents
B. Inspection and audits
C. Estimate budget
D. Risk register
Section: Closing
<<<<<< =================== >>>>>>
Q. 884: Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
A. organizational skills
B. technical skills
C. communication skills
D. hard skills
Section: Initiation
<<<<<< =================== >>>>>>
Q. 885: Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
A. Expert judgment
B. Forecasting methods
C. Earned value management
D. Analytical techniques
Section: Executing
<<<<<< =================== >>>>>>
Q. 886: A required input for Create WBS is a project:
A. quality plan.
B. schedule network.
C. management document update.
D. scope statement.
Section: Planning
<<<<<< =================== >>>>>>
Q. 887: The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
A. Executing.
B. Initiating.
C. Monitoring and Controlling.
D. Planning.
Section: Executing
<<<<<< =================== >>>>>>
Q. 888: Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
A. Supportive
B. Directive
C. Controlling
D. Instructive
Section: Executing
<<<<<< =================== >>>>>>
Q. 889: A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
A. Urgent information need
B. Sensitivity of information
C. Project environment
D. Ease of use
Section: Executing
<<<<<< =================== >>>>>>
Q. 890: A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
A. Urgent information need
B. Sensitivity of information
C. Project environment
D. Ease of use
Section: Executing