Q. 61: An intentional activity to modify a nonconforming product or product component is called:
A. defect repair
B. work repair
C. corrective action
D. preventive action
Section: Executing
<<<<<< =================== >>>>>>
Q. 62: Which of the following could be organizational process assets?
A. Historical information
B. Industry standards
C. Organization infrastructure
D. Marketplace conditions
Section: Executing
<<<<<< =================== >>>>>>
Q. 63: Which of the following is an input to the Qualitative Risk Analysis process?
A. Risk register
B. Risk data quality assessment
C. Risk categorization
D. Risk urgency
Section: Initiation
<<<<<< =================== >>>>>>
Q. 64: Which items are components of a project management plan?
A. Change management plan, process improvement plan, and scope management plan
B. Agreements, procurement management plan. and work performance information
C. Schedule management plan, project schedule, and resource calendars
D. Scope baseline, project statement of work, and requirements traceability matrix
Section: Planning
<<<<<< =================== >>>>>>
Q. 65: A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
A. risk management plan
B. human resource management plan
C. scope management plan
D. procurement management plan
Section: Planning
<<<<<< =================== >>>>>>
Q. 66: Which Process Group and Knowledge Area include the Sequence Activities process?
A. Executing Process Group and Project Time Management
B. Executing Process Group and Project Cost Management
C. Planning Process Group and Project Time Management
D. Planning Process Group and Project Cost Management
Section: Initiation
<<<<<< =================== >>>>>>
Q. 67: A key tool and technique used in define scope is:
A. Templates, forms, and standards
B. Decomposition
C. Expert judgment
D. Project management methodology
Section: Mix Questions
Justification in favor of the correct answer:
Expert judgment is used to analyze the information needed to develop a project scope statement. It is applied to any technical details.
<<<<<< =================== >>>>>>
Q. 68: An output of the Develop Project Team process is:
A. Organizational process assets
B. Enterprise environmental factors updates.
C. Project staff assignments.
D. Organizational charts and position descriptions
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 69: Which tool or technique is required in order to determine the project budget?
A. Cost of quality
B. Historical relationships
C. Project management software
D. Forecasting
Section: Planning
<<<<<< =================== >>>>>>
Q. 70: In scope control, it is important to determine the cause of any unacceptable variance relative to the scope baseline. This can be done through:
A. Root cause analysis
B. Control charts
C. Inspections
D. Project performance measurements
Section: Mix Questions
Justification in favor of the correct answer:
Variance analysis is a tool and technique for control scope. Project performance measurements are used to assess the magnitude of variance, to determine the cause of the variance, and to decide whether a corrective or preventive action is required.