PMI PMP-Project Management Professional Practice Exam Q. 51 to 60
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 51: The Chart below is an example of a:
A. Responsibility assignment matrix (RAM)
B. Work breakdown structure (WBS)
C. RACI chart
D. Requirements traceability matrix
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 52: Which of the following is a tool or technique used in the Determine Budget process?
A. Variance analysis
B. Three-point estimating
C. Bottom-up estimating
D. Historical relationships
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 53: The scope management plan is a subsidiary of which project document?
A. Schedule management plan
B. Project management plan
C. Quality management plan
D. Resource management plan
Section: Initiation
<<<<<< =================== >>>>>>
Q. 54: As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
A. BAC
B. EAC
C. ETC
D. WBS
Section: Initiation
<<<<<< =================== >>>>>>
Q. 55: Which of the following strategic considerations often results in project authorization?
A. Customer requests and/or issue resolution
B. Stakeholder expectations and/or strategic opportunity (business need)
C. Technological advancement and/or senior executive request
D. Market demand and/ or legal requirements
Section: Executing
<<<<<< =================== >>>>>>
Q. 56: Which is a tool or technique used in Define Scope?
A. Templates. forms, and standards
B. Change requests
C. Product analysis
D. Project assumptions
Section: Initiation
<<<<<< =================== >>>>>>
Q. 57: What type of project structure is a hierarchically organized depiction of the resources by type?
A. Organizational breakdown structure (OBS)
B. Resource breakdown structure (RBS)
C. Work breakdown structure (WBS)
D. Project breakdown structure (PBS)
Section: Initiation
<<<<<< =================== >>>>>>
Q. 58: Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
A. Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses
Section: Planning
<<<<<< =================== >>>>>>
Q. 59: Which tool is used to develop technical details within the project management plan?
A. Expert judgment
B. Project management methodology
C. Project management information system (PMIS)
D. Project selection methods
Section: Planning
<<<<<< =================== >>>>>>
Q. 60: Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
A. Requirements traceability matrix
B. Work breakdown structure (WBS) dictionary
C. Requirements management plan
D. Requirements documentation
Section: Initiation