PMI PMP-Project Management Professional Practice Exam Q. 41 to 50
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 41: An output of the Manage Stakeholder Engagement process is
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log
Section: Initiation
<<<<<< =================== >>>>>>
Q. 42: In which process might a project manager use risk reassessment as a tool and technique?
A. Perform Qualitative Risk Analysis
B. Risk Control
C. Monitor and Control Project Work
D. Plan Risk Responses
Section: Executing
<<<<<< =================== >>>>>>
Q. 43: Change request status updates are an output of which process?
A. Perform Integrated Change Control
B. Direct and Manage Project Execution
C. Close Project or Phase
D. Monitor and Control Project Work
Section: Executing
<<<<<< =================== >>>>>>
Q. 44: A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
A. Plan Stakeholder Management
B. Identify Stakeholders
C. Manage Stakeholder Engagement
D. Control Stakeholder Engagement
Section: Initiation
<<<<<< =================== >>>>>>
Q. 45: Which of the following procurement processes results in the awarding of a procurement contract?
A. Administer Procurements
B. Close Procurements
C. Conduct Procurements
D. Plan Procurements
Section: Executing
<<<<<< =================== >>>>>>
Q. 46: When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
A. event.
B. response.
C. perception.
D. impact.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 47: A regression line is used to estimate:
A. Whether or not a process is stable or has predictable performance.
B. How a change to the independent variable influences the value of the dependent variable
C. The upper and lower specification limits on a control chart
D. The central tendency, dispersion, and shape of a statistical distribution.
Section: Planning
<<<<<< =================== >>>>>>
Q. 48: Which document describes the necessary information to determine if a project is worth the required investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
Section: Initiation
<<<<<< =================== >>>>>>
Q. 49: Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
Section: Initiation
<<<<<< =================== >>>>>>
Q. 50: Which of the following investigates the likelihood that each specific risk will occur?
A. Risk register
B. Risk audits
C. Risk urgency assessment
D. Risk probability and impact assessment
Section: Initiation
Access the full Database of All Questions

An expert on R&D, Online Training and Publishing. He is M.Tech. (Honours) and is a part of the STG team since inception.