PMI PMP-Project Management Professional Practice Exam Q. 31 to 40
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 31: The zero duration of milestones in project planning occurs because milestones:
A. Are unpredictable and challenge the Plan Schedule Management process.
B. Occur at random times in the project plans
C. Represent a moment in time such as a significant project point or event.
D. Represent both significant and insignificant points in the project and are difficult to anticipate.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 32: An input required to develop a preliminary project scope statement is:
A. Organizational Structure
B. Organizational Process Assets
C. Organizational Matrix
D. Organizational Breakdown Structures
Section: Initiation
<<<<<< =================== >>>>>>
Q. 33: Which items are an output of the Perform Integrated Change Control process?
A. Work performance reports
B. Accepted deliverables
C. Project management plan updates
D. Organizational process assets
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 34: Design of experiments (DOE) should be used during which of the following processes?
A. Perform Quality Assurance
B. Total Quality Management
C. Perform Quality Control
D. Plan Quality
Section: Executing
<<<<<< =================== >>>>>>
Q. 35: Co-location is a tool and technique of:
A. Develop Human Resource Plan.
B. Manage Project Team.
C. Develop Project Team.
D. Acquire Project Team.
Section: Planning
<<<<<< =================== >>>>>>
Q. 36: Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?
A. Coaching
B. Avoidance
C. Consensus
D. Influencing
Section: Closing
<<<<<< =================== >>>>>>
Q. 37: At the start of a typical project life cycle, costs are:
A. low, peak as work is carried out, and drop as the project nears the end.
B. low become steady as work is carried out and increase as the project nears the end,
C. high, drop as work is carried out, and increase as the project nears the end.
D. high, become low as work is carried out and drop as the project nears the end.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 38: An input to the Plan Procurement Management process is:
A. Source selection criteria.
B. Market research.
C. A stakeholder register.
D. A records management system.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 39: In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
A. Schedule
B. Quality
C. Communications
D. Cost
Section:Planning
<<<<<< =================== >>>>>>
Q. 40: A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
A. Historical information and the lessons-learned database.
B. Historical information and the stakeholder register
C. Organizational process assets and the lessons-learned database.
D. Project documents and historical information.
Section: Initiation
Access the full Database of All Questions

An expert on R&D, Online Training and Publishing. He is M.Tech. (Honours) and is a part of the STG team since inception.