Q. 581: Which input will be used when tasked with developing the human resource plan?
A. Project management plan
B. Activity resource requirements
C. Resource calendar
D. Project staff assignments
Section: Planning
<<<<<< =================== >>>>>>
Q. 582: Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
A. cost Plus Fixed Fee Contract (CPFF)
B. Cost Plus Incentive Fee Contract (CPIF)
C. Firm Fixed Price Contract (FFP)
D. Fixed Price with Economic Price Adjustment Contract (FP-EPA)
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 583: Which of the following lists contain processes that are included within Project Procurement Management?
A. Plan purchases and acquisitions, plan contracting, request seller responses, select sellers
B. Plan purchases and acquisitions, request seller responses, select sellers, schedule control
C. Plan purchases and acquisitions, acquire project team, request seller responses, select sellers
D. Plan purchases and acquisitions, acquire project team, contract approval, select sellers
Section: Planning
<<<<<< =================== >>>>>>
Q. 584: Written change requests should be required on:
A. All projects, large and small
B. Only large projects
C. Projects with a formal configuration management system in place
D. Projects for which the cost of a change control system can be justified
Section: Mix Questions
Justification in favor of the correct answer:
A system is needed for careful monitoring of changes made to the requirements. Use of written change requests encourages the individuals asking for changes to take responsibility for their requests and reduces frivolous requests that may adversely affect the project.
<<<<<< =================== >>>>>>
Q. 585: What are the formal and informal policies, procedures, and guidelines that could impact how the project’s scope is managed?
A. Organizational process assets
B. Enterprise environmental factors
C. Project management processes
D. Project scope management plan
Section: Executing
<<<<<< =================== >>>>>>
Q. 586: The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
A. appetite
B. tolerance
C. threshold
D. management
Section: Initiation
<<<<<< =================== >>>>>>
Q. 587: Who MUST know when a risk event occurs so that a response can be implemented?
A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department
Section: Initiation
<<<<<< =================== >>>>>>
Q. 588: Which of the following tools and techniques are utilized in the Close Project or Phase process?
A. Project management information system
B. Product analysis
C. Expert judgment
D. Inspection
Section: Closing
<<<<<< =================== >>>>>>
Q. 589: All projects involve some extent of change because they involve work that is unique in some fashion. Therefore, it is important that a project management plan includes a:
A. Description of the change request process
B. Configuration management plan
C. Methodology for preventive action to avoid the need for excessive changes
D. A work authorization system
Section: Mix Questions
Justification in favor of the correct answer:
A configuration management plan is part of a project management plan to document how configuration management will be performed on the project.
<<<<<< =================== >>>>>>
Q. 590: Which type of analysis would be used for the Plan Quality process?
A. Schedule
B. Checklist
C. Assumption
D. Cost-Benefit