Q. 561: The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:
A. interview technique
B. information gathering technique
C. Delphi technique
D. feedback technique
Section: Executing
<<<<<< =================== >>>>>>
Q. 562: In project development, schedule information such as who will perform the work, where the work will be performed, activity type, and WBS classification are examples of:
A. Activity attributes
B. Constraints
C. Data in the WBS repository
D. Refinements
Section: Mix Questions
Justification in favor of the correct answer:
Identifying activity attributes is helpful for further selection and sorting of planned activities. They are used for schedule development and for report formatting purposes.
<<<<<< =================== >>>>>>
Q. 563: Which type of tool would be used for quality planning activity?
A. Schedule Analysis
B. Checklist Analysis
C. Assumption Analysis
D. Cost-Benefit Analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 564: Prototype development may be used as a tool for which of the following risk response strategies?
A. Avoid
B. Accept
C. Mitigate
D. Exploit
Section: Initiation
<<<<<< =================== >>>>>>
Q. 565: Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
A. The customer and functional managers
B. The risk owners and stakeholders
C. The sponsors and stakeholders
D. The project management team
Section: Planning
<<<<<< =================== >>>>>>
Q. 566: Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days. What should be your concern?
A. There is a cost underrun.
B. There is a cost overrun.
C. May not meet the deadline.
D. The project is 20 days behind schedule.
Section: Executing
<<<<<< =================== >>>>>>
Q. 567: The project management processes presented in the PM BOK Guide should:
A. always be applied uniformly.
B. be selected as appropriate by the sponsor.
C. be selected as appropriate by the project team.
D. be applied based on ISO guidelines.
Section: Closing
<<<<<< =================== >>>>>>
Q. 568: Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
A. Power/influence grid
B. Power/interest grid
C. Influence/impact grid
D. Salience model
Section: Planning
<<<<<< =================== >>>>>>
Q. 569: A tool or technique used during the Administer Procurements process is:
A. Expert judgment.
B. Bidder conference.
C. Procurement negotiation.
D. Performance reporting.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 570: Which of the following choices is a contract closure tool or technique?
A. Contract plan
B. Procurement plan
C. Closure process
D. Procurement audits