Q. 441: Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
A. Organizational standard processes
B. Marketplace conditions
C. Historical information
D. Templates
Section: Initiation
<<<<<< =================== >>>>>>
Q. 442: The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
A. Work packages.
B. Accepted deliverables.
C. The WBS dictionary.
D. The scope baseline.
Section: Planning
<<<<<< =================== >>>>>>
Q. 443: Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
A. Work breakdown structure
B. Organizational breakdown structure
C. Resource breakdown structure
D. Bill of materials
Section: Planning
<<<<<< =================== >>>>>>
Q. 444: Which Manage Communications tool or technique focuses on identifying and managing barriers?
A. Communication methods
B. Information technology
C. Communication models
D. Information management systems
Section: Planning
<<<<<< =================== >>>>>>
Q. 445: Expected monetary value (EMV) is computed by which equation?
A. Value of each possible outcome multiplied by the probability of occurrence
B. Value of each possible outcome multiplied by the probability of non-occurrence
C. Multiplying the value of each possible outcome by the probability of occurrence and adding the products together
D. Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together
Section: Executing
<<<<<< =================== >>>>>>
Q. 446: The run chart created during the Perform Quality Control process on a project is used to show the:
A. relationship between two variables
B. data points plotted in the order in which they occur
C. most common cause of problems in a process
D. frequency of occurrence
Section: Executing
<<<<<< =================== >>>>>>
Q. 447: In an organization with a projectized organizational structure, who controls the project budget?
A. Functional manager
B. Project manager
C. Program manager
D. Project management office
Section: Planning
<<<<<< =================== >>>>>>
Q. 448: Which of the following is a group decision-making technique?
A. Brainstorming
B. Focus groups
C. Affinity diagram
D. Plurality
Section: Planning
<<<<<< =================== >>>>>>
Q. 449: What component of the project scope definition defines project exclusions?
A. Project boundaries
B. Project constraints
C. Project assumptions
D. Project objectives
Section: Planning
<<<<<< =================== >>>>>>
Q. 450: Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing this dual reporting relationship factor?
A. Functional manager
B. Project manager
C. Functional manager supported by the project manager