Q. 451: The Human Resource Management processes are:
A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.
Section: Executing
<<<<<< =================== >>>>>>
Q. 452: You are beginning a new project staffed with a virtual team located across five countries. To help avoid conflict in work priorities among your team members and their functional managers, you ask the project sponsor to prepare a:
A. Memo to team members informing them that they work for you now
B. Project charter
C. Memo to the functional managers informing them that you have authority to direct their employees
D. Human resource management plan
Section: Mix Questions
Justification in favor of the correct answer:
Although the project charter cannot stop conflicts from arising, it can provide a framework to help resolve them because it describes the project manager’s authority to apply organizational resources to project activities.
<<<<<< =================== >>>>>>
Q. 453: The Perform Integrated Change Control process occurs in which Process Group?
A. Initiating
B. Executing
C. Monitoring and Controlling
D. Planning
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 454: Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?
A. Earned value performance
B. Trend analysis
C. Cost-benefit analysis
D. Variance analysis
Section: Executing
<<<<<< =================== >>>>>>
Q. 455: Which process group contains the processes performed to finalize all activities?
A. Planning Process Group
B. Executing Process Group
C. Monitoring and Controlling Process Group
D. Closing Process Group
Section: Executing
<<<<<< =================== >>>>>>
Q. 456: Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
A. project documents updates.
B. project management plan updates.
C. change requests.
D. work performance information.
Section: Executing
<<<<<< =================== >>>>>>
Q. 457: Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
A. Plan Cost Management
B. Plan Scope Management
C. Plan Stakeholder Management
D. Plan Schedule Management
Answer: C
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 458: A thorough review of will help identify potential risks to the project.
A. Risk identification checklists based on historical information and knowledge
B. The project’s change control system
C. The project’s mission statement
D. The project’s budget
Section: Planning
Justification in favor of the correct answer:
Risk identification checklists can be developed based on historical information and knowledge that has been accumulated from previous similar projects and from other sources of information.
<<<<<< =================== >>>>>>
Q. 459: An input of the Control Schedule process is the:
A. resource calendar.
B. activity list.
C. risk management plan.
D. organizational process assets.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 460: Which of the following is an output of Define Scope?
A. Project scope statement
B. Project charter
C. Project plan
D. Project schedule
Section: Planning