Q. 421: Progressively elaborating high-level information into detailed plans is performed by the:
A. project management office
B. portfolio manager
C. program manager
D. project manager
Section: Planning
<<<<<< =================== >>>>>>
Q. 422: Which tool or technique is used in the Plan Scope Management process?
A. Document analysis
B. Observations
C. Product analysis
D. Expert judgment
Section: Planning
<<<<<< =================== >>>>>>
Q. 423: The Create WBS process is in which of the following Project Management Process Groups?
A. Planning
B. Monitoring and Controlling
C. Executing
D. Initiating
Section: Planning
<<<<<< =================== >>>>>>
Q. 424: The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
A. Control Schedule.
B. Quality Control.
C. Perform Integrated Change Control.
D. Develop Schedule.
Section: Executing
<<<<<< =================== >>>>>>
Q. 425: Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
A. Historical relationships
B. Dependency determination
C. Bottom-up estimating
D. Rolling wave planning
Section: Executing
<<<<<< =================== >>>>>>
Q. 426: Because your project is slated to last five years, you believe rolling wave planning is appropriate, it provides information about the work to be done:
A. Throughout all project phases
B. For successful completion of the current project phase
C. For successful completion of the current and subsequent project phases
D. In the next project phase
Section: Mix Questions
Justification in favor of the correct answer:
Rolling wave planning provides progressive detailing of the work to be accomplished throughout the life of the project, indicating that planning and documentation are iterative and ongoing processes.
<<<<<< =================== >>>>>>
Q. 427: The diagram given below is an example of a:
A. Risk breakdown structure (RBS).
B. Project team.
C. SWOT Analysis.
D. Work breakdown structure (WBS).
Section: Initiation
<<<<<< =================== >>>>>>
Q. 428: An imposed date for completion of the project by the customer is an example of a project:
A. deliverable
B. assumption
C. constraint
D. exclusion
Section: Executing
<<<<<< =================== >>>>>>
Q. 429: Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
A. The influence of the stakeholders’ increases, the cost of changes increases.
B. The influence of the stakeholders’ decreases, the cost of changes increases.
C. The influence of the stakeholders’ increases, the cost of changes decreases.
D. The influence of the stakeholders decreases, the cost of changes decreases.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 430: Which of the following tools and techniques is used in the Verify Scope process?
A. Inspection
B. Variance analysis
C. Expert judgment
D. Decomposition
Section: Initiation