Q. 251: The procurement process that documents agreements and related documentation for future reference are known as:
A. Plan Procurements.
B. Control Procurements.
C. Close Procurements.
D. Conduct Procurements.
Section: Closing
<<<<<< =================== >>>>>>
Q. 252: The scope management plan and scope baseline are contained in:
A. organizational process assets
B. a requirements traceability matrix
C. the project charter
D. the project management plan
Section: Initiation
<<<<<< =================== >>>>>>
Q. 253: You are a personnel management specialist recently assigned to a project team working on a team-based reward and recognition system. The other team members also work in the human resources department. The project charter should be issued by:
A. The project manager
B. The client
C. A sponsor
D. A member of the PMO who has jurisdiction over human resources
Section: Mix Questions
Justification in favor of the correct answer:
The project charter should be issued by a project initiator or sponsor who formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. The project charter should not be issued by the project manager, although, the project manager can assist in its development.
<<<<<< =================== >>>>>>
Q. 254: Which of the following is an information gathering technique in Identify Risks?
A. Influence diagrams
B. Brainstorming
C. Assumption analysis
D. SWOT analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 255: Which tool or technique is effective in a project in which the deliverable is not a service or result?
A. Inspection
B. Variance analysis
C. Decomposition
D. Product analysis
Section: Executing
<<<<<< =================== >>>>>>
Q. 256: Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Closing
Section: Planning
<<<<<< =================== >>>>>>
Q. 257: When the business objectives of an organization change, project goals need to be:
A. realigned.
B. performed.
C. improved.
D. controlled.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 258: In which of the following types of organizations is resource availability moderate to high?
A. Weak matrix
B. Balanced matrix
C. Strong matrix
D. Projectized
Section: Executing
<<<<<< =================== >>>>>>
Q. 259: To which process is work performance information an input?
A. Contract administration
B. Direction and management of project execution
C. Create WBS
D. Qualitative risk analysis
Section:Executing
<<<<<< =================== >>>>>>
Q. 260: Which of the following response strategies are appropriate for negative risks or threats?
A. Share, Accept, Transfer, or Mitigate
B. Exploit, Enhance, Share, or Accept
C. Mitigate, Share, Avoid, or Accept
D. Avoid, Mitigate, Transfer, or Accept
Section: Initiation