Q. 231: Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
A. Define Activities
B. Direct and Manage Project Work
C. Develop Project Management Plan
D. Develop Project Charter
Section: Planning
<<<<<< =================== >>>>>>
Q. 232: All the following are project baselines that are generally part of the project management plan EXCEPT:
A. Technical
B. Scope
C. Time
D. Cost
Section: Mix Questions
Justification in favor of the correct answer:
Scope, time, and cost are examples of project baselines to be part of the project management plan.
<<<<<< =================== >>>>>>
Q. 233: When does risk monitoring and control occur?
A. At project initiation
B. During work performance analysis
C. Throughout the life of the project
D. At project milestones
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 234: What do composite organizations involve?
A. Functional and project managers
B. Functional managers only
C. Project managers only
D. Technical managers and project managers
Section: Closing
<<<<<< =================== >>>>>>
Q. 235: Plan-do-check-act is also known as:
A. prevention over inspection.
B. statistical sampling.
C. management responsibility.
D. continuous improvement.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 236: Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
A. Identify Risks
B. Perform Qualitative Risk Analysis
C. Plan Risk Management
D. Perform Quantitative Risk Analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 237: Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A. Project Risk Management
B. Project Integration Management
C. Project Communications Management
D. Project Quality Management
Section:Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 238: Which schedule network analysis technique modifies the project schedule to account for limited resources?
A. Human resource planning
B. Fast-tracking
C. Critical chain method
D. Rolling wave planning
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 239: When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
A. Interactive communication
B. Claims administration
C. Conflict management
D. Performance reporting
Section: Closing
<<<<<< =================== >>>>>>
Q. 240: You have been directed to establish a change control system for your company, but must convince your colleagues to use it. To be effective, the change control system must include:
A. Procedures that define how project documents may be changed
B. Specific change requests expected on the project and plans to respond to each one
C. Performance reports that forecast project changes
D. A description of the functional and physical characteristics of an item or system
Section: Mix Questions
Justification in favor of the correct answer:
A change control system is a collection of formal, documented procedures that define the process used to control change and approve or reject changes to project documents, deliverables, or baselines. It includes the paperwork, tracking systems, and approval levels necessary to authorize changes.
Access the full Database of All Questions

An expert on R&D, Online Training and Publishing. He is M.Tech. (Honours) and is a part of the STG team since inception.