Q. 1751: Who is responsible for the quality of the project deliverables?
A. The project champion
B. The project team
C. Stakeholders
D. Customers
Section: Planning
Justification in favor of the correct answer:
The project team (the individuals completing the project work) is responsible for the quality of the project deliverables.
<<<<<< =================== >>>>>>
Q. 1752: What is the amount of time that a schedule activity can be delayed without delaying the successor activity?
A. Free Float
B. Total Float
C. Project Float
D. Soft logic
Section: Planning
Justification in favor of the correct answer:
Free Float is the amount of time that a schedule activity can be delayed without delaying the successor activity. Free Float can be determined by taking EF – ES + 1.
<<<<<< =================== >>>>>>
Q. 1753: Which of the following statements is not true about WBS?
A. It is created by the project team.
B. It should not change.
C. It ensures that all work on the project is covered.
D. It organizes and defines the total scope of work.
Section: Planning
Justification in favor of the correct answer:
The WBS can sometimes get updated during the Define activities process or due to approved changes to scope.
<<<<<< =================== >>>>>>
Q. 1754: When should a schedule baseline be created in the project?
A. At the end of the project and used to compare schedule performance on status reports
B. At the beginning of the project and then ignored because management does not care
C. At the end of the project and included in the archive
D. At the beginning of the project and used during the project to gauge performance
Section: Planning
Justification in favor of the correct answer:
The schedule baseline is created at the beginning of the project and is used during the project to gauge performance.
<<<<<< =================== >>>>>>
Q. 1755: Which measurement of a product characteristic has only two results, pass or fail?
A. Variable sampling
B. Statistical sampling
C. Attribute sampling
D. Binary sampling
Section: Monitoring & Controlling
Justification in favor of the correct answer:
When a measurement has only two results either conforms or does not conform, it is known as attribute sampling.
<<<<<< =================== >>>>>>
Q. 1756: Three ways to estimate the project costs are:
A. Analogous, bottom-up, activity based costing
B. Bottom-up, Parametric, or Analogous
C. Level staffing cost, Monte Carlo, Bottom-up
D. Analogous, Monte Carlo, Resource planning
Section: Planning
Justification in favor of the correct answer:
Three methods of estimating costs are bottom up, parametric, and analogous estimating. Other methods include Three-point estimates and expert judgement.
<<<<<< =================== >>>>>>
Q. 1757: Which describes how cost variances will be managed?
A. Cost management plan
B. Cost baseline
C. Cost estimate
D. Chart of accounts
Section: Planning
Justification in favor of the correct answer:
Cost Management Plan is the document that sets out the format and establishes the activities and criteria for planning, structuring, and controlling the project costs. The Cost Management Plan is contained in or is a subsidiary plan of the project Management plan.
<<<<<< =================== >>>>>>
Q. 1758: Which of the following describes SWOT?
A. An analysis of strengths, weakness, options, and timing
B. An analysis of strengths, weakness, opportunities, and threats
C. An elite project team that comes in and fixes project risks and threats
D. Ratings of 1 to 100
Section: Planning
Justification in favor of the correct answer:
SWOT analysis is part of risk identification and examines the strengths, weakness, opportunities, and threats of the project to make certain all possibilities for risk identification are covered.
<<<<<< =================== >>>>>>
Q. 1759: Which of the following skills are considered “hard” skills?
A. Negotiation skills
B. Social skills
C. Technical skills
D. People skills
Section: Executing
Justification in favor of the correct answer:
Technical skills are considered “hard” skills. People skills and social skills are referred to as “soft” skills.
<<<<<< =================== >>>>>>
Q. 1760: The basis of identification for current or potential problems to support later claims or new procurements is provided by:
A. A risk urgency assessment.
B. The scope baseline.
C. Work performance information.
D. Procurement audits.
Section: Executing