Q. 1731: Which of the following can be displayed as an S-Curve?
A. Estimate at completion
B. TCPI
C. CPI and SPI
D. Cost performance baseline
Section: Planning
Justification in favor of the correct answer:
The Cost Performance baseline is often said to be displayed as an s-curve. The S-Curve is a graphic display of cumulative cost, labor hours, percentage of work, or other quantities, plotted against time. The S-Curve can also be used to show planned value, earned value, and actual cost of project work.
<<<<<< =================== >>>>>>
Q. 1732: What is Plan quality?
A. Carrying out of cost benefit analysis
B. Determining applicable quality standards and processes to satisfy the quality requirements
C. Flowcharting
D. Deriving a quality policy
Section: Planning
Justification in favor of the correct answer:
The Quality Planning process involves identifying quality standards relevant to the project and determining how to satisfy them.
<<<<<< =================== >>>>>>
Q. 1733: Risk assessment should be performed:
A. On all projects
B. Only on projects with high visibility
C. Only on projects with tight budgets
D. Prior to initiating a project
Section: Planning
Justification in favor of the correct answer:
All projects should have some level of risk assessment as part of planning.
<<<<<< =================== >>>>>>
Q. 1734: Why do projects have a work breakdown structure (WBS)?
A. The WBS shows activities of the project.
B. The WBS organizes and defines the project scope.
C. The WBS identifies areas of the project that require additional planning.
D. The WBS identifies the project.
Section: Planning
Justification in favor of the correct answer:
WBS organizes and defines the project scope.
<<<<<< =================== >>>>>>
Q. 1735: Which of the following can’t be tracked using the WBS?
A. Time
B. Cost
C. Quality
D. description of work
Section: Planning
Justification in favor of the correct answer:
Time, cost and description of work (scope) can be tracked using the WBS, but not quality.
<<<<<< =================== >>>>>>
Q. 1736: A WBS is a deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. Which of the following best describes the WBS?
A. A scope artifact that is archived after completion
B. A pictorial representation of the project team’s organization
C. A pictorial representation of the activities on a project
D. A pictorial representation of project deliverables
Section: Planning
Justification in favor of the correct answer:
WBS is pictorial representation of project deliverables.
<<<<<< =================== >>>>>>
Q. 1737: The ________ skills of general management are often the _______to do:
A. Soft, hardest
B. General, last
C. Hard, easiest
D. Tactical, hardest
Section: Executing
Justification in favor of the correct answer:
Soft skills, such as handling people, are difficult to learn. People skills are almost always the hardest to learn and to master, and usually must be done on the job. Technical skills are learned more easily and often taught in school.
<<<<<< =================== >>>>>>
Q. 1738: According to the PMBOK, which of the following is not an input to Plan Quality?
A. Stakeholder register
B. Risk register
C. Requirements documentation
D. Fishbone diagrams
Section: Planning
Justification in favor of the correct answer:
Project management plan, stakeholder register, requirements documentation, risk register, enterprise environmental factor and organizational process assets are inputs to the Plan Quality process.
<<<<<< =================== >>>>>>
Q. 1739: Which of the following is done after Define Activities is completed?
A. Plan Quality
B. Develop Schedule
C. Estimate Activity Durations
D. Sequence Activities
Section: Planning
Justification in favor of the correct answer:
Activity lists, activity attributes and schedule milestones are the outputs from Define Activities. Next we sequence activities, estimate activity resources, estimate activity durations, then finally develop schedule.
<<<<<< =================== >>>>>>
Q. 1740: Which process is not included in Project Time Management?
A. Define Activities
B. Sequence Activities
C. Estimate Activity Resources
D. Create Work Breakdown Structure (WBS)
Section: Planning
Justification in favor of the correct answer:
Create WBS is done in the Project Scope Management process.
<<<<<< =================== >>>>>>