PMI PMP-Project Management Professional Practice Exam Q. 171 to 180
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 171: How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder’ analysis?
A. Keep satisfied
B. Keep informed
C. Manage closely
D. Monitor
Section: Planning
<<<<<< =================== >>>>>>
Q. 172: A complete set of concepts, terms, and activities that make up an area of specialization is known as:
A. a Knowledge Area
B. a Process Group
C. program management
D. portfolio management
Section: Initiation
<<<<<< =================== >>>>>>
Q. 173: Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
A. Conduct Procurements.
B. Close Procurements.
C. Administer Procurements.
D. Plan Procurements.
Section: Executing
<<<<<< =================== >>>>>>
Q. 174: Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the PERT estimate for the expected duration of the work package?
A. 45 weeks
B. 70 weeks
C. 90 weeks
D. 140 weeks
Section: Mix Questions
<<<<<< =================== >>>>>>
Q. 175: Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
A. Acquisition
B. Negotiation
C. Virtual team
D. Pre-assignment
Section: Planning
<<<<<< =================== >>>>>>
Q. 176: At which stage of the project should certain factors such as the unavailability of human resources due to constraint be considered?
A. Initiation
B. Execution
C. Planning
D. Monitoring and Controlling
Section: Planning
<<<<<< =================== >>>>>>
Q. 177: Which item is an example of a personal assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group
Section: Initiation
<<<<<< =================== >>>>>>
Q. 178: Which of the following is an example of the simplest fixed-price contract?
A. Purchase requisition
B. Purchase order
C. Verbal agreement
D. Request for quote
Section: Closing
<<<<<< =================== >>>>>>
Q. 179: What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
A. Decomposition
B. Benchmarking
C. Inspection
D. Checklist analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 180: The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
A. Timing
B. Methodology
C. Risk categories
D. Budgeting
Section: Planning
Access the full Database of All Questions

An expert on R&D, Online Training and Publishing. He is M.Tech. (Honours) and is a part of the STG team since inception.