PMI PMP-Project Management Professional Practice Exam Q. 111 to 120
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 111: The probability and impact matrix is primarily used to:
A. Quantify risk issues for trends during a quality audit.
B. Develop a risk register for risk planning.
C. Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.
D. Define risk and compare impacts during Perform Quantitative Risk Analysis.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 112: Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
A. Portfolio
B. Project
C. Program
D. Operations
Section: Executing
<<<<<< =================== >>>>>>
Q. 113: How is quality control performed?
A. By identifying quality standards that are relevant to the project and determining how to satisfy them
B. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed
C. By ensuring that the entire project team has been, adequately trained in quality assurance process
D. By applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 114: Types of internal failure costs include:
A. inspections.
B. equipment and training
C. lost business
D. reworking and scrapping
Section: Closing
<<<<<< =================== >>>>>>
Q. 115: A disadvantage associated with virtual teams is that they:
A. Require communication technology that is not readily available
B. Create difficulties when including people with disabilities.
C. Often cannot accommodate teams that work different hours or shifts
D. Create the possibility for misunderstandings to arise.
Section: Executing
<<<<<< =================== >>>>>>
Q. 116: At the end of the project, what will be the value of SV?
A. Positive
B. Zero
C. Negative
D. Greater than one
Section: Closing
<<<<<< =================== >>>>>>
Q. 117: The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 118: A project manager should communicate to stakeholders about resolved project issues by updating the:
A. project records
B. project reports
C. stakeholder notifications
D. stakeholder register
Section: Executing
<<<<<< =================== >>>>>>
Q. 119: Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?
A. Product
B. Cost-benefit
C. Stakeholder
D. Research
Section: Planning
<<<<<< =================== >>>>>>
Q. 120: As you are working on your telecommunications project, even though you are using agile methods, you realize you are preparing an extensive amount of data and information. You regularly share data with your project team. Your last team meeting focused on the number of change requests and also the start and finish dates of activities in your schedule. They are examples of:
A. Key performance indicators
B. Work performance reports
C. Work performance data
D. Work performance information
Section: Mix Questions
Justification in favor of the correct answer:
Work performance data are the raw observations and measurements identified during activities performed to carry out the work of the project. Other examples are the reported percent of work physically completed, quality and technical performance measures, number of defects, actual costs, and actual durations.
Access the full Database of All Questions