Q. 121: One of the tools and techniques of the Manage Project Team process is:
A. organization charts
B. ground rules
C. organizational theory,
D. conflict management.
Section: Executing
<<<<<< =================== >>>>>>
Q. 122: When sequencing activities, what does the common acronym FF stand for?
A. Fixed Fee
B. Free Float
C. Fixed Finish
D. Finish-to-Finish
Section: Closing
<<<<<< =================== >>>>>>
Q. 123: Which input provides suppliers with a clear set of goals, requirements, and outcomes?
A. Procurement statement of work
B. Purchase order
C. Source selection criteria
D. Bidder conference
Section: Executing
<<<<<< =================== >>>>>>
Q. 124: Which of the following is a tool and technique used to monitor risk?
A. Technical performance measurement
B. Cost performance baseline
C. Benchmarking
D. Cost of quality
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 125: Which element does a project charter contain?
A. Management reserves
B. Work breakdown structure
C. Stakeholder list
D. Stakeholder register
Section: Initiation
<<<<<< =================== >>>>>>
Q. 126: Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
A. Project Plan
B. Responsibility Matrix
C. Issue Log
D. Scope Document
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 127: The Following is a network diagram for a project:
What is the critical path for the project?
A. A-B-D-G
B. A-B-E-G
C. A-C-F-G
D. A-C-E-G
Section: Planning
<<<<<< =================== >>>>>>
Q. 128: Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?
A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline
Section: Executing
<<<<<< =================== >>>>>>
Q. 129: Which item is a formal proposal to modify any document, deliverable, or baseline:
A. Change request
B. Requirements documentation
C. Scope baseline
D. Risk urgency assessment
Section: Planning
<<<<<< =================== >>>>>>
Q. 130: Which of the following is a project constraint:
A. Twenty-five percent staff turnover is expected.
B. The technology to be used is cutting-edge.
C. Project leadership may change due to volatile political environment.
D. The product is needed in 250 days.
Section: Initiation