PMI PMP-Project Management Professional Practice Exam Q. 961 to 970
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 961: What are the potential drawbacks John may encounter by creating a bottom-up budget?
A. It is inaccurate
B. It is very time-consuming
C. It is hard to report
D. It is difficult to budget for unknown risks
Section:Planning
Justification in favor of the correct answer:
Bottom-up budgets are calculated by estimating and adding up each individual component to come up with a total. The main drawback is they are very time consuming. However, they are very accurate.
<<<<<< =================== >>>>>>
Q. 962: The term “change requests” as it refers to managing the project team primarily deals with changes.
A. Project plan
B. Schedule
C. Staffing
D. WBS
Section: Executing
Justification in favor of the correct answer:
Requested staffing changes are an output of managing the project team. This may include hiring, replacing or transferring team members.
<<<<<< =================== >>>>>>
Q. 963: You have sent a purchase order to ABC Enterprise. Which of the following is true?
A. You are requesting payment from ABC Enterprise for a product/service already provided.
B. You intend to sell a product/service to ABC Enterprise.
C. You intend to bid for a project from ABC Enterprise.
D. You intend to purchase product/service from ABC Enterprise.
Section: Planning
Justification in favor of the correct answer:
You intend to purchase something from ABC Enterprise. Hence options A, B, and C are incorrect.
<<<<<< =================== >>>>>>
Q. 964: Online, classroom, computer-based, and on-the-job are all examples of types of:
A. Ideas
B. Training
C. Tactics
D. Communication
Section: Executing
Justification in favor of the correct answer:
Online, classroom, computer-based, and on-the-job are types of training.
<<<<<< =================== >>>>>>
Q. 965: Which of the following is used to create the WBS?
A. Product analysis
B. Facilitated workshops
C. Decomposition
D. Alternative identification
Section: Planning
Justification in favor of the correct answer:
Product analysis, Facilitated Workshops and Alternatives identification are tools and techniques of Define Scope.
<<<<<< =================== >>>>>>
Q. 966: A project has three critical paths. How does this affect the project?
A. It makes it easier to manage.
B. It increases the risk of schedule slippage.
C. It requires more people.
D. It makes it more expensive.
Section: Monitoring & Controlling
Justification in favor of the correct answer:
More than one critical path will increase the project risk. This means that there are multiple chains of activities on which if there are any delays, the project will be delayed.
<<<<<< =================== >>>>>>
Q. 967: Which of the following methods of estimating will provide the most accurate estimate?
A. Top-down estimating
B. Top-down budgeting
C. Bottom-up estimating
D. Parametric estimating
Section Planning
Justification in favor of the correct answer:
Bottom-up estimating takes the longest to complete of all the estimating approaches, but it is the most accurate estimating method.
<<<<<< =================== >>>>>>
Q. 968: Your project requires an electrician at week three. This is an example of which of the following?
A. Organizational interfaces
B. Resource requirements
C. Contractor requirements
D. Resource constraints
Section Planning
Justification in favor of the correct answer:
The project requires the electrician, a project role, this is a resource requirement.
<<<<<< =================== >>>>>>
Q. 969: Which of the following involves determining a project cost estimate based on the sum of individual work package estimates?
A. Bottom-up estimating
B. Analogous estimating
C. Parametric estimating
D. Expert judgment
Section Planning
Justification in favor of the correct answer:
Bottom-up estimating means rolling up the cost of individual activities or work packages to get a project total
<<<<<< =================== >>>>>>
Q. 970: Perform Quality assurance is:
A. Definition of organizational quality practices
B. Ensuring six sigma compliance
C. Application of Pareto charts to project sample points
D. Process of auditing the quality requirements and the results and ensure appropriate quality standards
Section: Executing
Justification in favor of the correct answer:
Perform Quality assurance involves auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards are used.