Q. 831: A tool and technique used during the Perform Qualitative Risk Analysis process is:
A. risk data quality assessment.
B. variance and trend analysis.
C. data gathering and representation techniques.
D. risk audits.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 832: Stakeholder management strategy is an output of:
A. Plan Communications.
B. Distribute Information.
C. Report Performance.
D. Identify Stakeholders.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 833: Each WBS component should be assigned a unique identifier from a code of accounts to:
A. Link the WBS to the bill of materials
B. Enable the WBS to follow a similar numbering system to that of the organization’s units as part of the organizational breakdown structure
C. Sum costs, schedule, and resource information
D. Link the WBS to the project management plan
Section: Mix Questions
Justification in favor of the correct answer:
The key document generated from the create WBS process is the actual WBS. Each WBS component is assigned a unique identifier to provide a structure for hierarchical summation of costs, schedule, and resource information.
<<<<<< =================== >>>>>>
Q. 834: Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
A. Cost Plus Award Fee Contract (CPAF)
B. Firm-Fixed -Price Contract (FFP)
C. Time and Material Contract (T&M)
D. Cost Plus Incentive Fee Contract (CPIF)
Section: Initiation
<<<<<< =================== >>>>>>
Q. 835: Which tool or technique is used to develop the human resource management plan?
A. Ground rules
B. Expert judgment
C. Team-building activities
D. Interpersonal skills
Section: Executing
<<<<<< =================== >>>>>>
Q. 836: Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?
A. Schedule performance index (SPI)
B. Cost performance index (CPI)
C. Cost variance (CV)
D. Planned value (PV)
Section: Closing
<<<<<< =================== >>>>>>
Q. 837: What is a technique used in the performance reporting process?
A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings
Section: Closing
<<<<<< =================== >>>>>>
Q. 838: An output of the Validate Scope process is:
A. A requirements traceability matrix.
B. The scope management plan.
C. Work performance reports.
D. Change requests.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 839: Which type of analysis is used as a general management technique within the Plan Procurements process?
A. Risk assessment analysis
B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis
Section: Initiation
<<<<<< =================== >>>>>>
Q. 840: You realize that projects represent change, and on your projects, you always seem to have a number of change requests to consider. In your current project to manage the safety of the nation’s cheese products and the testing methods used, you decided to prepare a formal change management plan. An often overlooked type of change request is:
A. Adding new subject matter experts to your team
B. Updates
C. Work performance information
D. Enhancing the reviews performed by your project’s governance board
Section: Mix Questions
Justification in favor of the correct answer:
Change requests may include corrective actions, preventive actions, defect repairs, or updates. Updates are changes to formally controlled project documents or plans to reflect modified or additional content.