PMI PMP-Project Management Professional Practice Exam Q. 741 to 750
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 741: Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
A. Reserve analysis
B. Three-point estimating
C. Parametric estimating
D. Analogous estimating
Section: Closing
<<<<<< =================== >>>>>>
Q. 742: What is one of the objectives of Project Risk Management?
A. Decrease the probability and impact of an event on project objectives.
B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.
C. Increase the probability and impact of positive events.
D. Removal of project risk.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 743: For a stakeholder with low interest and high power, the project manager should:
A. Monitor the stakeholder.
B. Manage the stakeholder closely.
C. Keep the stakeholder satisfied.
D. Keep the stakeholder informed.
Section: Executing
<<<<<< =================== >>>>>>
Q. 744: A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
A. cultural differences of team members
B. possibility of communication misunderstandings
C. costs associated with travel
D. costs associated with technology
Section: Planning
<<<<<< =================== >>>>>>
Q. 745: Fast tracking is a schedule compression technique used to shorten the project schedule without changing the project scope. Which of the following can result from fast-tracking?
A. The risk of achieving the shortened project time is increased.
B. The critical path will have a positive total float.
C. Contingency reserves are released for redeployment by the project manager.
D. Duration buffers are added to maintain a focus on planned activity durations.
Section: Executing
<<<<<< =================== >>>>>>
Q. 746: Stakeholder satisfaction should be managed as a key project:
A. Benefit
B. Initiative
C. Objective
D. Process
Section: Initiation
<<<<<< =================== >>>>>>
Q. 747: A project manager who communicates to the project team though email is using which type of communication?
A. Formal
B. Informal
C. Horizontal
D. Unofficial
Section: Executing
<<<<<< =================== >>>>>>
Q. 748: What is the number of stakeholders, if the project has 28 potential communication channels?
A. 7
B. 8
C. 14
D. 16
Section: Closing
<<<<<< =================== >>>>>>
Q. 749: Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
A. Control chart
B. Flowchart
C. Run chart
D. Pareto chart
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 750: Power, urgency, and legitimacy are attributes of which stakeholder classification model?
A. Salience
B. Influence/impact
C. Power/interest
D. Power/influence
Section: Initiation