Q. 541: Decomposition is a technique used for both WBS development and activity definition. Which following statement best describes the role decomposition plays in activity definition as compared to creating the WBS?
A. The final output is described in terms of work packages in the WBS.
B. The final output is described as deliverables or tangible items.
C. The final output is described as schedule activities.
D. Decomposition is used the same way in scope definition and activity definition.
Section: Mix Questions
Justification in favor of the correct answer:
The final output is described as schedule activities. In the create WBS process, the final output is described as deliverables or tangible items. In the define activities process, the final output is described as activities.
<<<<<< =================== >>>>>>
Q. 542: Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
A. Estimate at completion
B. Cost performance
C. Schedule performance
D. To-complete performance
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 543: Managing procurement relationships and monitoring contract performance are part of which process?
A. Conduct Procurements
B. Plan Procurements
C. Administer Procurements
D. Close Procurements
Section: Executing
<<<<<< =================== >>>>>>
Q. 544: Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
A. Collect Requirements
B. Direct and Manage Project Execution
C. Monitor and Control Project Work
D. Develop Project Management Plan
Section: Planning
<<<<<< =================== >>>>>>
Q. 545: Which of the following is an input to Direct and Manage Project Execution?
A. Requested changes
B. Approved change requests
C. Work performance information
D. Implemented defect repair
Section: Executing
<<<<<< =================== >>>>>>
Q. 546: What is a tool to improve team performance?
A. Staffing plan
B. External feedback
C. Performance reports
D. Co-location
Section: Executing
<<<<<< =================== >>>>>>
Q. 547: Which type of chart is a graphic representation of a process showing the relationships among process steps?
A. Control
B. Bar
C. Flow
D. Pareto
Section: Planning
<<<<<< =================== >>>>>>
Q. 548: Plan Communications Management develops an approach and plan for project communications based on stakeholders’ needs and requirements and:
A. Available organizational assets
B. Project staff assignments
C. Interpersonal skills
D. Enterprise environmental factors
Section: Initiation
<<<<<< =================== >>>>>>
Q. 549: Which is used to solicit proposals from prospective sellers?
A. Procurement statement of work
B. Resource calendars
C. Procurement document
D. Independent estimates
Section: Planning
<<<<<< =================== >>>>>>
Q. 550: What would you as a project manager focus on while crashing a schedule?
A. Accelerating the non-critical path tasks
B. Accelerating as many tasks as possible
C. Accelerating the tasks on the critical path
D. Skipping certain tasks
Section: Planning
Justification in favor of the correct answer:
Accelerating tasks on the non-critical path would not impact the project schedule as the critical path tasks form the longest duration path in a project network of tasks.