Q. 371: Which risk response strategy is common for both positive and negative risks?
A. Share
B. Accept
C. Mitigate
D. Transfer
Section: Executing
<<<<<< =================== >>>>>>
Q. 372: Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
A. Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates
Section: Initiation
<<<<<< =================== >>>>>>
Q. 373: What are the Project Procurement Management processes?
A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Section:Executing
<<<<<< =================== >>>>>>
Q. 374: The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing
Section: Initiation
<<<<<< =================== >>>>>>
Q. 375: Which of the following is a tool and technique for Estimate Activity Durations?
A. Parametric estimating
B. Monte Carlo analysis
C. Alternatives analysis
D. Bottom-up estimating
Section: Planning
<<<<<< =================== >>>>>>
Q. 376: Which of the following tools and techniques is used in the Develop Project Team process?
A. Acquisitions
B. Organizational theories
C. Team-building activities
D. Virtual teams
Section: Initiation
<<<<<< =================== >>>>>>
Q. 377: Which process is included in the Project Integration Management Knowledge Area?
A. Manage Project Team
B. Collect Requirements
C. Sequence Activities
D. Direct and Manage Project Work
Section: Initiation
<<<<<< =================== >>>>>>
Q. 378: Scope verification is PRIMARILY concerned with which of the following?
A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 379: Which of the following is an output of the Perform Integrated Change Control process?
A. Project document updates
B. Organizational process assets updates
C. Change requests
D. Deliverables
Section: Executing
<<<<<< =================== >>>>>>
Q. 380: To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
A. scope creep.
B. a change request.
C. work performance information.
D. deliverables.
Section: Executing