PMI PMP-Project Management Professional Practice Exam Q. 331 to 340
Largest Questions Bank with All Unique Questions prepared by Project Management Experts as per the latest PMBOK
(Quickly Review Your Skills before appearing for PMI PMP Certification Exam)
Set of 10 Questions
Correct Answer has been Highlighted in RED
Q. 331: Activities on the critical path have which type of float?
A. Zero free float
B. Zero or negative float
C. Negative and positive float
D. Zero or positive float
Section:Executing
<<<<<< =================== >>>>>>
Q. 332: Which of the following is an output of the Information Distribution Process?
A. Project calendar
B. Communication management plan
C. Requested changes
D. Communication requirement plan
Section: Planning
<<<<<< =================== >>>>>>
Q. 333: During which process group is the quality policy determined?
A. Initiating
B. Executing
C. Planning
D. Controlling
Section: Planning
<<<<<< =================== >>>>>>
Q. 334: The scope management plan and scope baseline are contained in:
A. organizational process assets
B. a requirements traceability matrix
C. the project charter
D. the project management plan
Section: Planning
<<<<<< =================== >>>>>>
Q. 335: The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
A. Push
B. Pull
C. Interactive
D. Iterative
Section: Initiation
<<<<<< =================== >>>>>>
Q. 336: Performance measurements are a tool and technique of the Control Schedule process. Which of the following measurements pertain to the Control Schedule process?
A. CPI, SPI
B. SV, CPI
C. CV, SV
D. SV, SPI
Section: Monitoring & Controlling
Justification in favor of the correct answer:
All options other than D have components that are used in the Control Cost process. Performance reviews measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress. If earned value management (EVM) is utilized, the schedule variance (SV) and schedule performance index (SPI) is used to assess the magnitude of schedule variations.
<<<<<< =================== >>>>>>
Q. 337: Which process occurs within the Monitoring and Controlling Process Group?
A. Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 338: Which tools or techniques will a project manager use for Developing the Project Team?
A. Negotiation
B. Roles and responsibilities
C. Recognition and rewards
D. Prizing and promoting
Section: Planning
<<<<<< =================== >>>>>>
Q. 339: An input of the Plan Procurement Management process is:
A. Make-or-buy decisions.
B. Activity cost estimates.
C. Seller proposals.
D. Procurement documents.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 340: Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
A. Project Time Management
B. Project Cost Management
C. Project Scope Management
D. Project Human Resource Management
Section: Initiation