Q. 1: Because the CPI is 0.56, what do we know about this project?
A. It can be finished on time if we crash the schedule.
B. We will need an extra 6 weeks to complete it.
C. The project is at budget risk.
D. None of the above.
Section: Monitoring & Controlling
Justification in favor of the correct answer:
A CPI less than 1.0 suggests that the project is going over budget.
<<<<<< =================== >>>>>>
Q. 2: Which activity is an input to the select sellers process?
A. Organizational process assets
B. Resource availability
C. Change control process
D. Team performance assessment
Section: Initiation
<<<<<< =================== >>>>>>
Q. 3: Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
A. Complete project phase
B. Project life
C. The project life cycle
D. Project cycle
Section: Planning
<<<<<< =================== >>>>>>
Q. 4: Which schedule development technique modifies the project schedule to account for limited resources?
A. Human resource planning
B. Fast-tracking
C. Critical chain method
D. Rolling wave planning
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 5: Perform Quality Control is accomplished by:
A. Identifying quality standards that are relevant to the project and determining how to satisfy them.
B. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.
C. Ensuring that the entire project team has been adequately trained in quality assurance processes.
D. Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.
Section: Monitoring and Controlling
<<<<<< =================== >>>>>>
Q. 6: A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A. Communication models.
B. Stakeholder participation.
C. Expert judgment
D. Enterprise environmental factors.
Section: Executing
<<<<<< =================== >>>>>>
Q. 7: In complex projects/ initiating processes should be completed:
A. Within a work package.
B. In each phase of the project.
C. To estimate schedule constraints.
D. To estimate resource allocations.
Section: Executing
<<<<<< =================== >>>>>>
Q. 8: Projects are separated into phases or subprojects; these phases include:
A. feasibility study, concept development, design, and prototype.
B. initiate, plan, execute, and monitor.
C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
D. Identify Stakeholders, develop concept, build, and test.
Section: Initiation
<<<<<< =================== >>>>>>
Q. 9: The end point of a project phase can be referred to as:
A. project failure
B. closing process
C. stage gate
D. lifecycle
Section: Closing
<<<<<< =================== >>>>>>
Q. 10: Which is an output of the Collect Requirements process?
A. Requirements traceability matrix
B. Project scope statement
C. WBS dictionary
D. Work performance measurements
Section: Initiation