Q. 721: Consider the following list of test process activities:

I. Analysis and design
II. Test closure activities
III. Evaluating exit criteria and reporting
IV. Planning and control
V. Implementation and execution

Which of the following places these in their logical sequence?

A. I, II,

III, IV and V.
B. IV, I, V, III and II.
C. IV, I, V, II and III.
D. I, IV, V, III and II.

<<<<<< =================== >>>>>>

Q. 722: Test objectives vary between projects and so must be stated in the test plan. Which one of the following test objectives might conflict with the proper tester mindset?

A. Show that the system works before we ship it.
B. Find as many defects as possible.
C. Reduce the overall level of product risk.
D. Prevent defects through early involvement.

<<<<<< =================== >>>>>>

Q. 723: Which test activities are supported by test data preparation tools?

A. Test management and control
B. Test specification and design
C. Test execution and logging
D. Performance and monitoring

<<<<<< =================== >>>>>>

Q. 724: Consider the following types of tools:

V. Test management tools
W. Static analysis tools
X. Modeling tools
Y. Dynamic analysis tools
Z. Performance testing tools

Which of the following of these tools is most likely to be used by developers?

A. W, X and Y
B. V, Y and Z
C. V, W and Z
D. X, Y and Z

<<<<<< =================== >>>>>>

Q. 725: What is a test condition?

A. An input, expected outcome, pre-condition and post-condition
B. The steps to be taken to get the system to a given point
C. Something that can be tested
D. A specific state of the software, e.g. before a test can be run

<<<<<< =================== >>>>>>

Q. 726: Which  of  the  following  general  testing  principles  are t rue?

Testing  shows the  presence of  defects  but  not the  absence of  defects
Testing  of combinations  of  inputs  and  outputs  will find  all  defects
Testing  should start after the  completion  of key  development tasks
Testing  of  safety-critical  software  is  similar to  testing  web  applications

A. I is true; II, III and IV are false
B. II is true; I, III and IV are false
C. I and II are true; III and N are false
D. II and III are true; I and IV are false

<<<<<< =================== >>>>>>

Q. 727: If the temperature falls below 18 degrees, the heating is switched on. When the temperature reaches 21 degrees, the heating is switched off. What is the minimum set of test input values to cover all valid equivalence partitions?

A. 15, 19 and 25 degrees
B. 17, 18, 20 and 21 degrees
C. 18, 20 and 22 degrees
D. 16 and 26 degrees

<<<<<< =================== >>>>>>

Q. 728: By  creating  future  tests  based  on the  results  of  previous  tests,  a  tester  is  demonstrating what type  of  informal  test  design  technique?

A. Security  testing
B. Non-functional  testing
C. Exploratory  testing
D. Interoperability  testing

<<<<<< =================== >>>>>>

Q. 729: What is the purpose of confirmation testing?

A. To confirm the users' confidence that the system will meet their business needs.

B. To confirm that a defect has been fixed correctly.

C. To confirm that no unexpected changes have been introduced or uncovered as a result of changes made.

D. To confirm that the detailed logic of a component conforms to its specification.

<<<<<< =================== >>>>>>

Q. 730: Which success factors are required for good tool support within an organization?

A. Acquiring the best tool and ensuring that all testers use it.

B. Adapting processes to fit with the use of the tool and monitoring tool use and benefits.

C. Setting ambitious objectives for tool benefits and aggressive deadlines for achieving them.

D. Adopting practices from other successful organizations and ensuring that initial ways of using the tool are maintained.

Correct Answer of the above Questions

Access the Full Database of all Questions

Quickstart to ISTQB Foundation Exam - Key Questions Answered

ISTQB Foundation Exam - Full Crash Course (Set of 35 Parts)

ISTQB Advanced CTAL Test Analysts Exam - Full Crash Course

ISTQB Advanced CTAL Test Manager Exam - Full Crash Course


ISTQB Certification Preparation Help Guide

Practical Roadmap to ISTQB Certification

Twelve Top Questions about ISTQB Certification
 

If you want to keep track of further articles on Software Testing,
I suggest you to subscribe my
RSS feed
.

You can also
Subscribe by E-mail
and get All New articles delivered directly to your Inbox.


Quick Navigation of Software Testing Genius

Get your Absolutely Free Copy of Several MS PowerPoint Presentations & E-Books related to ISTQB, HP Load Runner, IBM RFT, HP QTP & QC Certification Exams, prepared by Popular Writers & Trainers, by writing to: Software.testing.genius@gmail.com

Full Study Material for Popular Certification Exams:

Study Material - HP QTP & QC Certification Exam

Study Material - HP LoadRunner Certification Exam

Study Material - IBM RFT Certification Exam

Consolidated Study Material - Testing & QA

Most Popular Topics in Demand:

Practical Roadmap to QTP Certification

Practical Roadmap to CSTE Certification

Rehearsal of QTP in 1 Hr. -  Interview Questions

Correct Answers to the Earlier Questions - Q. 711 to Q 720 are as under:

Question No.

Correct Answer

Q. 711

A

Q. 712

A

Q. 713

D

Q. 714

C

Q. 715

B

Q. 716

C

Q. 717

B

Q. 718

C

Q. 719

C

Q. 720

D

 

Comments :

0 comments ↓


Leave Your Comments: (*) Marked Fields are Mandatory

You can apply basic formatting to the text

Name *
 
Email Address *
 
Website
 
Speak your mind
characters
sex hikayeleri