Q. 11: What is a project risk?
A. A risk directly related to the test object
B. The possibility of a negative or undesirable
outcome
C. The identification, analysis, prioritization, and control of risk
D. A risk related to management and control of the project
<<<<<< =================== >>>>>>
Q. 12: Which of the following puts the levels of TMM in the proper order?
A. Initial, Definition, Integration, Management and Measurement, Optimization
B. Initial, Integration, Definition, Management and Measurement, Optimization
C. Initial, Integration, Definition, Optimization, Management and Measurement
D. Initial, Definition, Integration, Optimization, Management and Measure; rent
<<<<<< =================== >>>>>>
Q. 13: What is test planning?
A. The activity of establishing or updating the principles, approach, and major objectives of the organization regarding testing
B. The activity of establishing or updating the scope, approach, resources and schedule of intended test activities
C. The activity of establishing or updating objectives, inputs, test actions, expected results, and execution preconditions
D. The activity of establishing or updating the method used to perform the actual test execution, either manual or automated
<<<<<< =================== >>>>>>
Q. 14: What is wide band Delphi?
A. An expert based test estimation technique that uses the collective wisdom of the team members.
B. Testing based on an analysis of the internal structure of the component or system.
C. A framework to describe the software development life cycle activities from requirements specification to maintenance.
D. The tracing of requirements through the layers of development documentation to components.
<<<<<< =================== >>>>>>
Q. 15: Which of the following statements is true?
A. The Critical Testing Processes model works only for organizations using the V-model software lifecycles
B. The Critical Testing Processes model works only for organizations using the agile software lifecycles
C. The Critical Testing Processes model works only for organizations using evolutionary software lifecycles
D. The Critical Testing Processes model works for organizations using any software lifecycles
<<<<<< =================== >>>>>>
Q. 16: Which of the following is the best description of a client�server application?
A. The application makes use of a web front end.
B. There is at least one computer that provides information to other computers.
C. There is one computer that provides information to dumb terminals.
D. The application(s) run on a single computer.
<<<<<< =================== >>>>>>
Q. 17: Which of the following best describes a difference between a sequential development model and an iterative one?
A. A sequential development model will always take longer than an iterative model, for a similar sized project.
B. A sequential development model guarantees that the customer will like the product, while the iterative model does not.
C. A sequential development model involves the users in testing mostly at the end of development, while the iterative model concentrates on the user perspective throughout development.
D. A sequential development model requires significant regression testing, while an iterative model does not.
<<<<<< =================== >>>>>>
Q. 18: Which of the following are included in test plans?
I. A schedule of events.
II. The set of test cases to be run.
III. The roles and responsibilities of stakeholders.
IV. The test data.
V. The test results and incidents raised.
A. I and II
B. II and III
C. II, IV and V
D. I and III
<<<<<< =================== >>>>>>
Q. 19: Which of the following would be an appropriate entry criterion from system testing into acceptance testing?
A. 100 per cent functional specification coverage.
B. 100 per cent business requirements coverage.
C. 100 per cent statement coverage.
D. 100 per cent path coverage.
<<<<<< =================== >>>>>>
Q. 20: Which of the following would give the best measure of progress against product quality?
A. The number of tests run against those planned.
B. The turnaround time for defects.
C. The number of high priority defects outstanding.
D. The time taken to run each test.
Read the correct Answers of the Above Questions
Read the Full Database of All Questions
Largest Database of Sample Papers – 1000+ Unique Questions for ISTQB Foundation Exam
ISTQB Foundation Exam – Full Crash Course (Set of 35 Parts)
ISTQB Advanced CTAL Test Analysts Exam – Full Crash Course
ISTQB Advanced CTAL Test Manager Exam – Full Crash Course
Consolidated Study Material – All ISTQB Certification Exams
What Successful Testers say about the Quality of this website
If you want to keep track of further articles on Software Testing,
I suggest you to subscribe my RSS feed.You can also Subscribe by E-mail and get All New articles delivered directly to your Inbox. |
Get your Absolutely Free Copy of Several MS PowerPoint Presentations & E-Booksrelated to ISTQB, HP Load Runner, IBM RFT, HP QTP & QC Certification Exams, prepared by Popular Writers & Trainers, by writing to:Software.testing.genius@gmail.com
Study Material for Certification Exams on Other Automation Tools:
Download Full Study Material – HP QTP & QC Certification Exams
Practical Roadmap to QTP Certification
Rehearsal of QTP in 1 Hr. – Interview Questions
Study Material – HP LoadRunner Certification Exams for All Modules
Rehearsal of LoadRunner in 1 Hr. – Interview Questions
Study Material – IBM RFT Certification Exam
Study Material to prepare for Manual Testing & QA:
Practical Roadmap to CSTE Certification
Consolidated Study Material – Testing & QA
Correct Answers to Earlier Questions – Q.1 to Q 10 are as under:
Question No. | Correct Answer |
Q. 1 | A |
Q. 2 | B |
Q. 3 | B |
Q. 4 | D |
Q. 5 | B |
Q. 6 | A |
Q. 7 | C |
Q. 8 | C |
Q. 9 | A |
Q. 10 | D |