Q. 981: Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
A. Plan Procurement Management
B. Control Procurements
C. Collect Requirements
D. Plan Cost Management
Section: Planning
<<<<<< =================== >>>>>>
Q. 982: As the project progresses, which of the following is routinely collected from the project activities?
A. Communication management activities
B. Change requests
C. Configuration verification and audit
D. Work performance information
Section: Executing
<<<<<< =================== >>>>>>
Q. 983: A temporary endeavor that creates a unique product or service is called a:
A. Project
B. Plan
C. Program
D. Portfolio
Section: Initiation
<<<<<< =================== >>>>>>
Q. 984: Rent-A-Computer Inc. will rent you a computer for $200 per day. Best Buy will lease it to you for a $750 down payment and $50 per day. When do the cost of renting and leasing become the same?
A. 09 Days
B. 08 Days
C. 12 Days
D. 05 Days
Section: Planning
Justification in favor of the correct answer:
If it takes “N” days, then, 200* N = 750 + 50*N. On solving for N, it is 5 days.
<<<<<< =================== >>>>>>
Q. 985: Which type of analysis is used to develop the communications management plan?
A. Product
B. Cost benefit
C. Stakeholder
D. Research
Section: Planning
<<<<<< =================== >>>>>>
Q. 986: Where are product requirements and characteristics documented?
A. Product scope description
B. Project charter
C. Preliminary project scope statement
D. Communications management plan
Section: Initiation
<<<<<< =================== >>>>>>
Q. 987: Which of the following is an example of schedule compression?
A. Activity sequencing
B. Resource leveling
C. Lead and lag adjusting
D. Crashing
Section: Executing
<<<<<< =================== >>>>>>
Q. 988: Activity cost estimates are quantitative assessments of the probable costs required to:
A. Create WBS.
B. complete project work.
C. calculate costs.
D. Develop Project Management Plan.
Section: Planning
<<<<<< =================== >>>>>>
Q. 989: During project selection, which factor is most important?
A. Types of constraints
B. Internal business needs
C. Budget
D. Schedule
Section: Planning
<<<<<< =================== >>>>>>
Q. 990: A project can be defined as a:
A. Temporary endeavor undertaken to create a unique product, service, or result
B. Temporary endeavor that produces repetitive outputs
C. Permanent endeavor undertaken to create a unique product, Service, or result
D. Permanent endeavor that produces repetitive outputs
Section: Initiation