Q. 531: Which of the following is NOT a reasonable test objective:
A. To find faults in the software
B. To prove that the software has no faults
C. To give confidence in the software
D. To find performance problems
<<<<<< =================== >>>>>>
Q. 532: Which of the following uses Impact Analysis most?
A. Component testing
B. Non-functional system testing
C. User acceptance testing
D. Maintenance testing
<<<<<< =================== >>>>>>
Q. 533: What type of review requires formal entry and exit criteria, including metrics:
A. Walkthrough
B. Inspection
C. Management review
D. Post project review
<<<<<< =================== >>>>>>
Q. 534: Maintenance means
A. Updating tests when the software has changed
B. Testing a released system that has been changed
C. Testing by users to ensure that the system meets a business need
D. Testing to maintain business advantage
<<<<<< =================== >>>>>>
Q. 535: A Test Plan Outline contains which of the following:-
i. Test Items
ii. Test Scripts
iii. Test Deliverables
iv. Responsibilities
A. I,ii,iii are true and iv is false
B. i,iii,iv are true and ii is false
C. ii,iii are true and i and iv are false
D. i,ii are false and iii , iv are true
<<<<<< =================== >>>>>>
Q. 536: All of the following might be done during unit testing except
A. Desk check
B. Manual support testing
C. Walkthrough
D. Compiler based testing
<<<<<< =================== >>>>>>
Q. 537: Which of the following is a requirement of an effective software environment?
I. Ease of use
II. Capacity for incremental implementation
III. Capability of evolving with the needs of a project
IV. Inclusion of advanced tools
A.I, II &III
B.I, II &IV
C.II, III&IV
D.I, III&IV
<<<<<< =================== >>>>>>
Q. 538: When testing a grade calculation system, a tester determines that all scores from 90 to 100 will yield a grade of A, but scores below 90 will not. This analysis is known as:
A. Equivalence partitioning
B. Boundary value analysis
C. Decision table
D. Hybrid analysis
<<<<<< =================== >>>>>>
Q. 539: The bug tracking system will need to capture these phases for each bug.
I. Phase injected
II. Phase detected
III. Phase fixed
IV. Phase removed
A. I, II and III
B. I, II and IV
C. II, III and IV
D. I, III and IV
<<<<<< =================== >>>>>>
Q. 540: Which of the following software change management activities is most vital to assessing the impact of proposed software modifications?
A. Baseline identification
B. Configuration auditing
C. Change control
D. Version control
Correct Answer of the above Questions
Access the Full Database of all Questions
Correct Answers to the Earlier Questions – Q. 521 to Q 530 are as under:
Question No. | Correct Answer |
Q. 521 | B |
Q. 522 | C |
Q. 523 | D |
Q. 524 | C |
Q. 525 | A |
Q. 526 | A |
Q. 527 | C |
Q. 528 | C |
Q. 529 | C |
Q. 530 | A |