Q. 201: The inputs for developing a test plan are taken from

A. Project plan
B. Business plan
C. Support plan
D. None of the above

<<<<<< =================== >>>>>>

none" class=MsoNormal>Q. 202: A tool that supports traceability, recording of incidents or scheduling of tests is

called:

 

A. A dynamic analysis tool

B. A test execution tool

C. A debugging tool

D. A test management tool

E. A configuration management tool

<<<<<< =================== >>>>>>

Q. 203: Which of the following is not a static testing technique

A. Error guessing
B. Walkthrough
C. Data flow analysis
D. Inspections

<<<<<< =================== >>>>>>

Q. 204: Which  document  specifies  the  sequence  of test  executions?

A. Test  procedure  specification
B. Test  design  specification
C. Test  case  specification
D. Test  plan

<<<<<< =================== >>>>>>

Q. 205: Inspections can find all the following except

A. Variables not defined in the code
B. Spelling and grammar faults in the documents
C. Requirements that have been omitted from the design documents
D. How much of the code has been covered

<<<<<< =================== >>>>>>

Q. 206: Which of the following is not a characteristic for Testability?

A. Operability
B. Observability
C. Simplicity
D. Robustness

<<<<<< =================== >>>>>>

Q. 207: Software testing accounts to what percent of software development costs?

A. 10-20
B. 40-50
C. 70-80
D. 5-10

<<<<<< =================== >>>>>>

Q. 208: Which  tool  can be  used to  support and  control  part of  the test  management  process?

A. Coverage  management  tool
B. Test  management  tool
C. Data  preparation  tool
D. Performance  testing  tool

<<<<<< =================== >>>>>>

Q. 209: If an expected result is not specified then:

A. We cannot run the test
B. It may be difficult to repeat the test
C. It may be difficult to determine if the test has passed or failed
D. We cannot automate the user inputs

<<<<<< =================== >>>>>>

Q. 210: When should we stop our testing?

A. This question is difficult to answer
B. The answer depends on the contract with the client, special requirements if any & risks your organization is willing to take
C. The answer depends on the experience & maturity of your developers
D. The answer should be standardized for the software development industry

Correct Answer of the above Questions

Access the Full Database of all Questions

Quickstart to ISTQB Foundation Exam - Key Questions Answered

ISTQB Foundation Exam - Full Crash Course (Set of 35 Parts)

ISTQB Advanced CTAL Test Analysts Exam - Full Crash Course

ISTQB Advanced CTAL Test Manager Exam - Full Crash Course


ISTQB Certification Preparation Help Guide

Practical Roadmap to ISTQB Certification

Twelve Top Questions about ISTQB Certification
 

If you want to keep track of further articles on Software Testing,
I suggest you to subscribe my
RSS feed
.

You can also Subscribe by E-mail
and get All New articles delivered directly to your Inbox.


Quick Navigation of Software Testing Genius

Get your Absolutely Free Copy of Several MS PowerPoint Presentations & E-Books related to ISTQB, HP Load Runner, IBM RFT, HP QTP & QC Certification Exams, prepared by Popular Writers & Trainers, by writing to: Software.testing.genius@gmail.com

Full Study Material for Popular Certification Exams:

Study Material - HP QTP & QC Certification Exam

Study Material - HP LoadRunner Certification Exam

Study Material - IBM RFT Certification Exam

Consolidated Study Material - Testing & QA

Most Popular Topics in Demand:

Practical Roadmap to QTP Certification

Practical Roadmap to CSTE Certification

Rehearsal of QTP in 1 Hr. -  Interview Questions

Correct Answers to the Earlier Questions - Q. 191 to Q 200 are as under:

Question No.

Correct Answer

Q. 191

B

Q. 192

A

Q. 193

A

Q. 194

D

Q. 195

D

Q. 196

B

Q. 197

D

Q. 198

C

Q. 199

C

Q. 200

B

 

Comments :

1 comments ↓

# 1 Nisha on 2012-05-17 15:21:30
Wonderful question bank



Leave Your Comments: (*) Marked Fields are Mandatory

You can apply basic formatting to the text

Name *
 
Email Address *
 
Website
 
Speak your mind
characters
sex hikayeleri