HP ALM 11.X Certification Exam Skill Test Q. 541 to 550
Newly Added Set of Questions helpful in HP Application Lifecycle Management 11.x Certification Exam code HPO M46
Objective Type / Multiple Choice Questions on HP ALM 11.X (QC � Quality Center 11.0) under the Series
(Quickly Review Your QC Skills before appearing for HP Certification Exam HPO M46)
Set of 10 Questions
Correct Answers to Earlier Questions – Q. 531 to Q 540 are at the end of the page:
Q. 541: As the project administrator of a project that is linked to a template project, what can you do?
A. Synchronize project customizations with the linked template project on demand
B. Roll back project customizations if problems are detected
C. Request suspension of template customizations being applied
D. Run verification prior to synchronization with the template project
<<<<<< =================== >>>>>>
Q. 542: DRAG DROP: Click the Task button. The process for Risk-Based Quality Management includes four steps. Identify the valid steps and place them in the correct order of execution.
Answer
<<<<<< =================== >>>>>>
Q. 543: Which type of data can be added to a Dashboard page?
A. Releases
B. Requirements
C. Reports
D. Graphs
<<<<<< =================== >>>>>>
Q. 544: What are supported test types out-of-the-box? (Select three.)
A. LOAD-TEST
B. CAPACITY-TEST
C. BLACK-BOX-TEST
D. LR-SCENARIO
E. QUICKTEST TEST
F. MANUAL
<<<<<< =================== >>>>>>
Q. 545: Which condition best allows leveraging of test configurations?
A. The test is configurable.
B. The test is manual.
C. The test is automated.
D. The test has parameters.
<<<<<< =================== >>>>>>
Q. 546: HOTSPOT: Click the Task Button. Click on the entity where data hiding can be configured.
Answer
<<<<<< =================== >>>>>>
Q. 547: Which application can you use to design a new Custom Report Template?
A. Microsoft Excel
B. Microsoft Word
C. HP Template Generator
D. ALM Template Manager
<<<<<< =================== >>>>>>
Q. 548: What can you do in the Configuration tab of a report?
A. Assign a report to a test step
B. Share reports
C. Link reports to test step
D. Select the report output format
<<<<<< =================== >>>>>>
Q. 549: What is required to create a Baseline Report?
A. The baseline must support the history template.
B. All report sections must support test configurations.
C. All report sections must support baselines.
D. The baseline must support the standard template.
<<<<<< =================== >>>>>>
Q. 550: Which integrations for HP Application Lifecycle Management are supported by the Free HP ALM Mylyn Connector? (Select two.)
A. Microsoft TFS connector
B. Bugzilla
C. Collabnet connector
D. CVS
E. Rational CiearQuest
Read the Correct Answer of the above Questions
Access the Full Database of All Questions
Correct Answers to Earlier Questions – Q.531 to Q 540 are as under:
Question No. | Correct Answer |
Q. 531 | A,D |
Q. 532 | B |
Q. 533 | B |
Q. 534 | B |
Q. 535 | A |
Q. 536 | D |
Q. 537 | B,D |
Q. 538 | B,E |
Q. 539 | C,D |
Q. 540 | B |