software testing genius

ISTQB Advanced Level Test Analyst Exam-Scenario Based Sample Questions-Q 51 to 60

Welcome to “Software Testing Genius”. Subscribe to my RSS feed for latest content on Software Testing.

ISTQB Advanced Level Test Analyst Exam Scenario Based Sample Questions: Q. 51 to 60

Deep study of this set of 53 questions out of which majority of them are scenario based & shall be of great help in getting success in ISTQB CTAL Advanced Level Test Analyst Exam.

All these questions are based upon the latest ISTQB Certified Tester Advanced Level Syllabus V 2007.

Set of 10 Questions (Q. 51 to 60)

Correct Answers of earlier Q. 41 to 50 are at the end of this page:

Q. 51: Consider the following excerpt from the Test Items section of a test plan. During System Test execution, the configuration management team shall deliver test releases to the test team every Monday

morning by 9:00 a.m. Each test release shall include a test item transmittal report. The test item transmittal report will describe the results of the automated build and smoke test associated with the release. Upon receipt of the test release, if the smoke test was successful, the test manager will install it in the test lab. Testing will commence on Monday morning once the new weekly release is installed.

Should the test team not receive a test release, or if the smoke test results are negative, or if the release will not install, or should the release arrive without a transmittal report, the test manager shall immediately contact the configuration management team manager. If the problem is not resolved within one hour, the test manager shall notify the project manager and continue testing against the previous week's release, if possible. If the test release fails installation, addition-ally the test analyst who attempted the installation shall file an incident report.

Assume that you are working as the test manager on this project. Suppose that you have received two working, installable, testable releases so far. On Monday of the third week, you do not receive the test release.

Which of the following courses of action is consistent with the test plan?

A. Filing an incident report describing the time and date at which you first noticed the missing test release

B. Creating a test procedure specification that describes how to install a test release

C. Sending an SMS text to the configuration management team manager

D. Send an e-mail to the project manager and the configuration management team manager

<<<<<< =================== >>>>>>

Q. 52: Assume that on Monday afternoon you finally receive a test release. When your lead test analyst attempts to install it, the database configuration scripts included in the installation terminate in midstream. An error message is presented on the database server in Cyrillic script, though the chosen language is U.S. English. At that point, the database tables are corrupted and any attempt to use the application under test results in various database connection error messages (which are at least presented in U.S. English).

Consider the following possible actions:

I. Notifying the configuration management team manager
II. Notifying the project manager
III. Filing an incident report
IV. Attempting to repeat the installation
V. Suspending testing
VI. Continuing testing

Which of the following sequence of actions is in the correct order, is the most reasonable, and is most consistent with the intent of the test plan?

A. I, II, V
B. V, I, IV,III, I
C. VI, II, I, III, IV
D. II, I, V

<<<<<< =================== >>>>>>

Sample Questions in context of ISTQB Advanced Level Technical Test Analyst Exam Syllabus - Chapter 10: People Skills & Team Composition


Q. 53: Assume you are a technical test analyst working on a banking project to upgrade an existing automated teller machine system to allow customers to obtain cash advances from supported credit cards. You are unable to obtain information about the minimum & maximum throughput of the connections between the automated teller machine and the payment processing networks, which is not included in the design specification. Which of the following is an example of a good way to communicate that problem in an e-mail?

A. "Until I receive a complete specification of throughput between ATMs and network, no progress on test design can occur"

B. "When will it be possible to know the maximum & minimum throughput of the ATM / network connections? Test design is impeded by a lack of clarity here."

C. "Here we go again. The design specification is incomplete and ambiguous."

D. Do not communicate the problem; just log the delaying effect of the information problem & be ready to explain the delays to the management when they ask.
 

Full Database of All Question for Advanced Level Test Analyst and Technical Test Analyst Exams

ISTQB Advanced CTAL Test Manager Exam - Full Crash Course for Download

Consolidated Study Material - All ISTQB Certification Exams

What Successful Testers say about the Quality of this website

If you want to keep track of further articles on Software Testing,
I suggest you to subscribe my
RSS feed
.

You can also Subscribe by E-mail
and get All New articles delivered directly to your Inbox.


Quick Navigation of Software Testing Genius

Get your Absolutely Free Copy of Several MS PowerPoint Presentations & E-Books related to ISTQB, HP Load Runner, IBM RFT, HP QTP & QC Certification Exams, prepared by Popular Writers & Trainers, by writing to: Software.testing.genius@gmail.com

Study Material for Certification Exams on Other Automation Tools:

Download Full Study Material - HP QTP & QC Certification Exams

Practical Roadmap to QTP Certification

Rehearsal of QTP in 1 Hr. -  Interview Questions

Study Material - HP LoadRunner Certification Exams for All Modules

Rehearsal of LoadRunner in 1 Hr. -  Interview Questions

Study Material - IBM RFT Certification Exam

Study Material to prepare for Manual Testing & QA:

Practical Roadmap to CSTE Certification

Consolidated Study Material - Testing & QA



Correct Answers to Above Questions - Q. 51 to Q 60 are as under:

Question No.

Correct Answer

Q. 51

C

Q. 52

B

Q. 53

B

Q. 54

 

Q. 55

 

Q. 56

 

Q. 57

 

Q. 58

 

Q. 59

 

Q. 60

 


Correct Answers to Earlier Questions - Q. 41 to Q 50 are as under:

Question No.

Correct Answer

Q. 41

D

Q. 42

A

Q. 43

A

Q. 44

C

Q. 45

B

Q. 46

C

Q. 47

D

Q. 48

C

Q. 49

B

Q. 50

A

 

Comments :

2 comments ↓

# 1 Rajesh on 2011-10-25 04:59:28
This is reaily amazing piece of information.

Thanks A Lot!


# 2 Rajeev Chauhan on 2011-10-29 07:15:38
Could anyone please tell me why we need to create COM and then utilize them in QTP.

Any help would be highly appreciated.

Raj



Leave Your Comments: (*) Marked Fields are Mandatory

You can apply basic formatting to the text

Name *
 
Email Address *
 
Website
 
Speak your mind
characters
sex hikayeleri