How to do Risk Analysis?
Welcome to “Software Testing Genius”. Subscribe to my RSS feed for latest content on Software Testing.

All software projects benefits from risk analysis. Even non-critical software, using risk analysis at the beginning of a project highlights the potential problem areas. This helps developers and managers to mitigate the risks. The tester uses the results of risk analysis to select the most crucial tests.

How Risk Analysis is done?

Risk analysis is a well-defined process that prioritizes modules for testing.

A risk contains following three components

(a) The risk (rI) associated with a project (i <- 1 to n).

(b) The probability of occurrence of a risk, (II).

(c) The impact of the risk (XI)

Risk analysis consists of first listing the potential problems and then assigning a probability and severity value for each identified problem. By ranking the results, the tester can identify the potential problems most in need of the immediate attention and select test cases to address those needs.

There are two methods of doing systematic risk analysis

Method-1: Using Risk Analysis Table (RAT)

Problem ID

Potential Problem (rI)

Probability of

occurrence(II)

Impact of

Risk (xI)

Risk Exposure
=(II) * (xI)

A

Loss of power

1

10

10

B

Corrupt file header

2

1

2

C

Unauthorized access

6

8

48

D

Databases not synchronized

3

5

15

E

Unclear user documentation

9

1

9

F

Lost sales

1

8

8

G

Slow throughput

5

3

15


Legend for the Risk Analysis Table is as under

Problem ID: Is a unique identifier associated with a risk.

Potential problem (rI):
It is a brief description of the problem.

Probability of occurrence (II):
It is a probability value on a scale of 1 (low) to 10 (high).

Severity of impact (XI):
It is a severity value on a scale of 1 (low) to 10 (high).

Risk exposure:
It is defined as the product of (II) and (XI).


In this Risk Analysis Table, the values of II and xI range from 1 to 10.

Multiplying the probability and severity values yields the risk exposure.

"The higher the risk exposure product, the more important it is to test for that condition".

Applying this rule to the above Risk Analysis Table, we will get the following rankings of the potential risks problems based on the product of risk-exposure.

The order of preference shall become
C-D-G-A-E-F-B

Although problems D and G have the same risk exposure, they differ by their probability and severity values.

Some organizations prefer to use this method of using Risk Analysis Table, while many others adopt risk-matrix analysis methodology.

Method-2: Risk Matrix Analysis (RMA)


A risk matrix allows the tester to evaluate and rank potential problems by giving more weight to the probability or severity value as necessary. The software tester uses the risk matrix to assign thresholds that classify the potential problems into priority categories.

There are four main methods of forming risk matrices

RMA Method - 1: Typically, the risk matrix contains four quadrants, as shown below.



Each quadrant in the above figure represents a priority class defined as under

Priority 1: High severity and high probability.

Priority 2: High severity and low probability.

Priority 3: Low severity and high probability.

Priority 4: Low severity and low probability.

We can see from the graph of above figure that a risk with high severity is deemed more important

than a problem with high probability. Thus, all risks mapped in the upper left quadrant fall into priority 2.

For example, the risk-e, which has high probability of occurrence but low severity of impact, is put under priority 3.

RMA Method - 2: For an entirely different w application, we may swap the definitions of priorities 2 and 3, as shown the figure below.



An organization favoring the above figure seeks to minimize the total number of defects by focusing on problems with a high probability of occurrence.

Dividing a risk matrix into quadrants is most common. The testers can determine the thresholds using different types of boundaries based on application specific needs.


RMA Method - 3: Diagonal band prioritization scheme.

If severity and probability tend to be equal weight i.e., if (II) = (XI)., then diagonal band prioritization scheme may be more appropriate. This is shown in the figure given below.



This threshold pattern is a compromise for those who have difficulty in selecting between priority-2 and priority-3 in the quadrant scheme.

RMA Method - 4: Some managers found out that the problems with high severity must be given the top priority, irrespective of the value of probability. This problem is solved with RMA Method-4 and is shown in following figure.



The remainder of the risk matrix is partitioned into several lower priorities, either as quadrants (RMA Method-1 and 2) or as diagonal bands (RMA Method-3).

Most Popular Topics in Demand:

Learn & Master Automation Tools Like : HP - QTP, IBM - RFT & HP - LoadRunner

Practical Roadmap to ISTQB Certification

Practical Roadmap to CSTE Certification

Practical Roadmap to QTP Certification


Please click here  -  To read Popular Articles on
effect of Global Recession & IT Sector



If you want to keep track of further articles on Software Testing, I suggest you to subscribe my RSS feed.

You can also Subscribe by E-mail
and get All New articles delivered directly to your Inbox.

 

Comments :


Leave Your Comments: (*) Marked Fields are Mandatory

Name *
 
Email Address *
 
Website
 
Speak your mind
  Subscribe
 
Sign up to receive daily updates
either via email or RSS!
   
Advertise Here
Advertise Here
Please use Vertical Scroll Bar
to View More Categories
 
 
     
 
 
advertise | privacy policy | copyright policy | online conduct home | about us | glossary | contact us | blog | email
Copyright © 2010. softwaretestinggenius.com. All Rights Reserved.
Website Designed & Developed By: 3dee Technologies